<strong>Forthbank</strong> <strong>Wind</strong> <strong>Energy</strong> <strong>Development</strong><br />

Timing of Construction Activities in Relation to Breeding Birds<br />

12.6.4 While scheduling the works programme to take place between April and September will<br />

minimise any disturbance impacts on passage and wintering wetland birds, it will mean that the<br />

works programme will coincide with the breeding bird season (March to July inclusive).<br />

12.6.5 Under the Wildlife and Countryside Act 1981 as amended by the Nature Conservation<br />

(Scotland) Act 2004, it is an offence with only limited exceptions, to:<br />

• intentionally or recklessly take, interfere with, damage or destroy the nest of any wild<br />

bird whilst it is in use or being built;<br />

• intentionally or recklessly take, interfere with or destroy the egg of any wild bird;<br />

• intentionally or recklessly disturb any wild bird listed on Schedule 1 while it is nest<br />

building, or at (or near) a nest containing eggs or young, or disturb the dependent<br />

young of such a bird.<br />

12.6.6 Consequently there will be a need to follow best practice during the construction of the<br />

proposed wind energy development to avoid the possibility of illegal damage, destruction or<br />

disturbance to occupied bird nests and ensure compliance with the legislation concerning<br />

disturbance to breeding birds.<br />

12.6.7 Construction activities are only expected to affect skylark; the only passerine (song bird)<br />

species which was recorded breeding in the grassland where the proposed turbines and<br />

subsidiary access tracks are to be located (the main site access track already exists). Skylark<br />

hold territories from as early as the start of March 25 so site clearance and preparation works<br />

will aim to be timed to take place as early as possible in March be<strong>for</strong>e peak breeding activity<br />

occurs.<br />

12.6.8 A pre-construction survey will be undertaken to identify any breeding activity and ascertain if<br />

any nesting birds are present on-site. If any active nests are found in close proximity to<br />

imminent construction activity then the work will either have to be re-scheduled or the nest site<br />

cordoned-off up to 50 metres. Construction operations will then be delayed within the cordon<br />

until the young have fledged and the nest becomes vacant. However, given that skylarks<br />

typically only start to nest in April 25 the likelihood of any active nests being present at the<br />

beginning of March is considered to be extremely low.<br />

12.6.9 If works are commenced across the site at this early stage, birds will have an opportunity to<br />

take potential disturbance into account in the process of selecting a nest site and are likely to<br />

select a site located away from any sources of disturbance.<br />

12.6.10 Compliance with the law will be achieved by the appointment of a suitably experienced<br />

ornithologist as Ecological Clerk of Works during the bird breeding season (March to July<br />

inclusive), to locate any active nests close to construction works shortly be<strong>for</strong>e these<br />

commence. Any active nests found will be cordoned off as described above. There will be a<br />

clear line of responsibility <strong>for</strong> ensuring these measures are adhered to.<br />

November 2010 Chapter 12 Page 82<br />