SECTION 017113<br />

MOBILIZATION<br />

PART 1 - GENERAL<br />

1.01 DESCRIPTION<br />

The work under this section <strong>of</strong> the specification shall include the establishment <strong>of</strong> <strong>of</strong>fices and<br />

other facilities on the project site and the movement <strong>of</strong> personnel, construction equipment, and<br />

supplies to the project site or to the vicinity <strong>of</strong> the project site to enable the Contractor to begin<br />

work on the other contract items that will be performed by the Contractor. This Item also includes<br />

all costs associated with bonding and insurance.<br />

PART 2 - PRODUCTS<br />

Not used.<br />

PART 3 - EXECUTION<br />

Not used.<br />

PART 4 - MEASUREMENT AND PAYMENT<br />

4.01 MEASUREMENT<br />

A. This Item will be measured on a Lump Sum (LS) basis as the work progresses.<br />

B. The maximum bid amount for this Item shall be 5% <strong>of</strong> the total amount bid for the project.<br />

4.02 PAYMENT<br />

Partial payments <strong>of</strong> the bid for Mobilization will be as follows. The adjusted contract amount for<br />

construction items as used below is defined as the total contract amount less the bid for<br />

Mobilization.<br />

A. When 1% <strong>of</strong> the adjusted contract amount for construction items is earned, 50% <strong>of</strong> the<br />

mobilization lump sum bid will be paid. Previous payments under this Item will be deducted<br />

from this amount.<br />

B. When 5% <strong>of</strong> the adjusted contract amount for construction items is earned, 75% <strong>of</strong> the<br />

mobilization lump sum bid will be paid. Previous payments under this Item will be deducted<br />

from this amount.<br />

C. When 10% <strong>of</strong> the adjusted contract amount for construction items is earned, 90% <strong>of</strong> the<br />

mobilization lump sum bid will be paid. Previous payments under this Item will be deducted<br />

from this amount.<br />

D. When 50% <strong>of</strong> the adjusted contract amount for construction items is earned, 100% <strong>of</strong> the<br />

mobilization lump sum bid will be paid. Previous payments under this Item will be deducted<br />

from this amount..<br />

END OF SECTION<br />

<strong>City</strong> <strong>of</strong> <strong>Frisco</strong> May 2012<br />

Standard Technical Specification Mobilization 017113-1