I. All lighting poles, fixtures, and arms which are removed with this project shall be delivered<br />

to the <strong>City</strong> <strong>of</strong> <strong>Frisco</strong> Public Works facility (11300 Research Road, <strong>Frisco</strong>, Texas 75034) by<br />

the Contractor and will remain the property <strong>of</strong> the <strong>City</strong> <strong>of</strong> <strong>Frisco</strong>.<br />

J. Texas State Law, Article 1436C, makes unlawful the operation <strong>of</strong> equipment or machines<br />

within 10-feet <strong>of</strong> any overhead electrical lines under danger against contact with high voltage<br />

overhead lines has been effectively guarded against pursuant to the provisions <strong>of</strong> the article.<br />

When construction operations require working near an overhead electrical line, the<br />

Contractor shall contact the owner/operator <strong>of</strong> the overhead electrical line to make adequate<br />

arrangements and to take necessary safety precautions to ensure that all laws, electrical line<br />

owner/operator requirements and standard industry safety practices are met.<br />

K. All materials and construction methods shall be in accordance with the details shown on the<br />

plans, the requirements <strong>of</strong> this Item and the pertinent requirements <strong>of</strong> the following items:<br />

a. TxDOT Item 616 “Performance Testing <strong>of</strong> Lighting Systems”<br />

b. TxDOT Item 620 “Electrical Conductors”<br />

PART 4 - MEASUREMENT AND PAYMENT<br />

4.01 MEASUREMENT<br />

A. This Item shall be measured on a per Each (EA) basis, complete in place.<br />

4.02 PAYMENT<br />

A. All work performed and materials furnished in accordance with this Item will be paid for at<br />

the unit bid price for “Luminaire Pole.” This price is full compensation for all material, labor,<br />

equipment, tools and superintendence necessary to complete the work.<br />

B. Foundations shall be paid for once regardless <strong>of</strong> extra work caused by obstructions.<br />

END OF SECTION<br />

<strong>City</strong> <strong>of</strong> <strong>Frisco</strong> May 2012<br />

Standard Technical Specification Luminaire Pole 265619-3