acceptable results are achieved. The automatic irrigation system will be available for the<br />

Contractor’s use. Any other water equipment deemed necessary by the Contractor will be<br />

provided by the Contractor at his expense.<br />

A. Watering: Use the automatic irrigation system to apply at least one-half (1/2”) inch <strong>of</strong> water<br />

over the entire planted area every three (3) days. Contractor shall water thoroughly and<br />

infrequently once grass is established to encourage deep root growth.<br />

B. Mowing: Once grass is established the planted area shall be mowed at least once a week<br />

during the growing season. Grass shall be mowed to a height <strong>of</strong> one (1”) inch and shall not<br />

exceed four inches (4”) in height. Mowing during dormant season will be done as necessary.<br />

C. Weed Control: No sooner than 45 days after grass has germinated any weed growth shall be<br />

arrested by applying MSMA broadcasted over the entire planted area. Additional applications<br />

<strong>of</strong> MSMA will be required to eliminate weed growth that continues to grow after the initial<br />

application. MSMA will only be used during the growing season. All weed growth during the<br />

dormant season will be controlled with spot applications <strong>of</strong> “Round-Up.” “Round- Up” will<br />

not be used until the grass is totally dormant.<br />

3.08 GRADING: All grading and placing <strong>of</strong> topsoil on any given area will be done prior to the<br />

beginning <strong>of</strong> this work. It will be the Contractor’s responsibility to maintain the existing grades<br />

and leave them in a true and even condition after planting turfgrass. Finish condition <strong>of</strong> turfgrass<br />

will be such that sod sits flush with paving (topsoil 1” below paving) and such that drainage<br />

grades and swales function and to not trap drainage on the paving.<br />

3.09 EROSION CONTROL: Throughout the project and the maintenance period for turfgrass, it is the<br />

Contractor’s responsibility to maintain the topsoil in place at specified grades. Topsoil and<br />

turfgrass losses due to erosion will be replaced by the Contractor until establishment and<br />

acceptance is achieved.<br />

3.10 CLEAN UP: This Contractor shall remove any excess material or debris brought onto the site or<br />

unearthed as a result <strong>of</strong> his turfgrass operations.<br />

3.11 GUARANTEE: This Contractor shall guarantee all materials used for this work to be the type,<br />

quality, and quantity specified.<br />

PART 4 –MEASUREMENT AND PAYMENT<br />

4.01 MEASUREMENT AND PAYMENT<br />

A. Measurement and Payment shall be specified in the Contract Documents.<br />

END OF SECTION<br />

<strong>City</strong> <strong>of</strong> <strong>Frisco</strong> May 2012<br />

Standard Technical Specification Turfgrass Planting 329223-5