SECTION 312316<br />

EXCAVATION (ROADWAY)<br />

PART 1 – GENERAL<br />

1.01 DESCRIPTION<br />

A. All material, labor, equipment, tools and superintendence necessary to furnish and install<br />

Excavation (Roadway) in accordance with Texas Department <strong>of</strong> Transportation Standard<br />

Specifications for Construction and Maintenance <strong>of</strong> Highways, Streets, and Bridges Item<br />

110..<br />

1.02 REFERENCES<br />

A. TxDOT Item 110.<br />

PART 2 - PRODUCTS<br />

2.01 MATERIALS<br />

A. Refer to TxDOT Item 110.2.<br />

B. All excavation shall be unclassified, and shall include the removal <strong>of</strong> all materials<br />

encountered, regardless <strong>of</strong> their nature or the manner in which they are removed.<br />

PART 3 - EXECUTION<br />

3.01 PREPARATION<br />

A. Refer to TxDOT Item 110.2<br />

B. Frequency <strong>of</strong> compaction testing shall not exceed one test for every three hundred linear feet<br />

300’ spacing or less, alternating from left quarter point to center line to right quarter point <strong>of</strong><br />

the cross section width.<br />

C. For density and moisture requirements <strong>of</strong> moisture treated excavation areas see Section<br />

32112 Moisture Treated Subgrade.<br />

PART 4 - MEASUREMENT AND PAYMENT<br />

4.01 MEASUREMENT<br />

A. Refer to TxDOT Item 110.3 or as indicated in the Contract Documents.<br />

B. The plan quantity will be determined through calculations and will be used for determining<br />

final quantity amounts for payment purposes. Contract adjustments may be made if the actual<br />

measured quantity varies by more or less than 5% <strong>of</strong> the total estimated plan quantity amount.<br />

Either the <strong>City</strong> or the Contractor may initiate this adjustment. If the adjustment is requested<br />

by the Contractor, the Contractor must obtain field measurements and calculations justifying<br />

<strong>City</strong> <strong>of</strong> <strong>Frisco</strong> May 2012<br />

Standard Technical Specification Excavation (Roadway) 312316-1