“O’ZLITINEFTGAZ” PC<br />

PFS “<strong>Surgil</strong> field complex costruction with valuable<br />

components retrieval”<br />

transport operation. The main components will be fuel combustion products in engines, and<br />

also inorganic dust during pipelines laying, trenching and excavation and etc. it is necessary<br />

to note, that impact on atmospheric air during construction will have short-term character,<br />

that practically will not affect background level of atmospheric pollution.<br />

According to intensity and impact level per time unit and unit of area the impact will<br />

be moderated and subject to inversion phenomenon the level of APP will low increase.<br />

As construction will be in the limited areas, dimensional coverage of impact will be<br />

limited by the necessary area and will have local character.<br />

Construction of pipelines will have temporary impact on soil and vegetation, upon<br />

termination of construction there will be executed restoration of the disturbed lands.<br />

Impact on surface waters has indirect character and is connected with withdrawal of<br />

water resources for industrial and drinking needs. Impact duration is the period of the<br />

designed constructions operation. Temporary dynamics of water withdrawal will be<br />

constant for fresh water.<br />

Distribution area, in case of sewage disposal to ponds-evaporators, is limited by the<br />

area of ponds-evaporators.<br />

Soils of investigated region concern to the main objects of impact. During this time<br />

intensity of impact is low, has the periodic character increasing during emergency<br />

emissions.<br />

Impact duration will not change, as this volume depends on time of the constructions<br />

operation. Impact will be continuous. Distribution areas will not extent. Impact character<br />

remains direct, as before.<br />

According to calculations of atmospheric pollution and operational experience of<br />

similar manufactures, it is possible to state, that the enterprise personnel will breathe air<br />

which quality corresponds to sanitary norms in the working areas, confirmed by Ministry of<br />

Health of the Republic of Uzbekistan.<br />

The soils of the investigated site of works and adjacent territories represent a zone of<br />

natural not high fertility (it is necessary irrigation). Small humus content does not allow<br />

developing to high vegetation types. Wind erosion and total amount of dusty particles are<br />

one of the reasons of soil degradation. Proceeding from the analysis of soil cover condition<br />

in the zone of object impact, it is possible to draw a conclusion:<br />

- object construction is carried out on the lands not convenient for<br />

agricultural crops.<br />

- main object impact is connected with additional disturbance of<br />

soils structure throughout gas pipeline route.<br />

In view of remoteness, surface waters are not objects of impact (only withdrawal for<br />

water supply).<br />

<strong>Volume</strong> 2. Part 1. EIS Project for <strong>Surgil</strong> field construction<br />

110