“Management of Ustyurt GCC infrastructure objects<br />
and <strong>Surgil</strong> GCF construction” UE »<br />
unit (sprayer). 3 persons will be involved in suppression of sulfate reducing bacteria in cuttings storage<br />
barn (technologist, unit driver and operator), duration of operation is 1 day. Scope and types of<br />
works, and also required quantity of materials for suppression of sulfate reducing bacteria in cuttings<br />
storage barn are resulted in table 8.1.<br />
Table 8.1 – Required quantity of materials, scope and types of works for suppression of sulfate<br />
reducing bacteria<br />
№№ Parameter name Unit<br />
Numerical<br />
value<br />
1 2 3 4<br />
1.<br />
Drilling cuttings treatment (moving, semi-liquid, fluid<br />
phase)<br />
m 3 345<br />
2. Blue copperas (СuSO 4 )х5Н 2 О kg 34.5<br />
3. SAS kg 690<br />
4. Process water m 3 0.7<br />
5. Tank truck with tank capacity to 6m 3 pcs. 1<br />
6. Reagent preparation for work (mixing in tank truck) un. 1<br />
7.<br />
Drilling cuttings surface treatment by 10% blue copperas<br />
and SAS solution<br />
un. 1<br />
8. Set in operation labor content person 2<br />
9. Duration of operation day 1<br />
10. Tank truck transportation under own power<br />
8.6.16. After realization of measures for drilling cuttings neutralization from hydrogen sulfide, on<br />
the expiry of 2 days, there are begins works on drilling cuttings neutralization/hardening.<br />
Whereas that drilling cuttings contains oil products in small amounts, it is necessary to add<br />
to binding substance – Portland cement quicklime in quantity to 20% from cement. Also, for<br />
reduction of consumable it is allowed bentonite addition in drilling cuttings, concerning to<br />
IV danger class – low-hazard dangerous wastes. In the case of EСO-2hardener use there is<br />
not required consumables.<br />
8.6.17. This stage of neutralization/hardening of the upper, moving, fluid layer of drilling cuttings is<br />
carried out manually or mechanically, at contractor discretion, under condition of strict observance<br />
of labor safety rules and operational experience on drilling wastes disposal in cuttings<br />
storage barn in the Southwest Gissar and Kandym fields.<br />
8.6.18. With a glance of DSW clarification and time of drilling cuttings sludge for DSW evaporation,<br />
it is accepted, that before the beginning of works on drilling cuttings neutralization/hardening,<br />
the liquid phase practically is absent and there is to 40-50sm of semi-fluid<br />
paste-like phase on barn surface (calculations of thickness volume of evaporation of water<br />
are resulted in Appendix 3).<br />
8.6.19. Prior to the beginning of works there is carried out preliminary survey of the barn territories,<br />
one of the barn sides near which there is the plain and cleared area for engineering, is accepted<br />
for base and there is made hollows excavation by excavator from three opposite sides<br />
into the perimeter of barn (in 3-4 hollows from each side) for liquid phase leavings running<br />
off from lenses. All works on drilling cuttings mixing and cuttings storage barn alignment<br />
are executed from the base side.<br />