“O’ZLITINEFTGAZ”<br />

open joint-stock company<br />

FS «Complex development of <strong>Surgil</strong> field<br />

with extracting of valuable components»<br />

CONCLUSION<br />

Feasibility study of the Project as for UGCC has been carried out by CMAI (Singapore)<br />

concerning marketing research together with «SAMSUNG ENGINEERING» and «HYUNDAI<br />

ENGINEERING» (Republic of Korea) concerning process technology and all-factory equipment. This<br />

process technology provides for gas and condensate processing with extracting of valuable<br />

components such as: HDPE, PP, sales gas.<br />

Based on the data provided DEI research was performed taking into account the State<br />

environmental expertise requirements made during DEI project examination.<br />

Results of hydrological and geological engineering survey of UGCC construction area have been<br />

studied thoroughly. In hydrogeological respect the area in question is arid. Ground waters occur at the<br />

depth of over 25.0m, they are strongly mineralized and unsuitable as potable or service water.<br />

Conducted geological engineering survey indicates the necessity of EGE-1 soils removal due to its<br />

macroporosity, subsiding and deformability. EGE-2 soils are also recommended for removal due to their<br />

physical-mechanical properties particularly unevenness of limestones spreading and thickness as well<br />

as marlaceous and argillaceous deposits dilatation. As the foundation soils EGE-3 soils are<br />

recommended for use and EGE-1 and EGE-2 soils are recommended to be changed for artificial soil<br />

and making impervious cushion of loamy soils by compacting.<br />

Domestic waste waters are to be purified at the treatment facilities. Normative clean waters are to<br />

be discharged to the ponds consisting of 5 maps with total area of 12ha for vaporizing.<br />

Method of purified process waste waters disposal to the Out Side Fence Limit of UGCC has not<br />

been worked out yet. Several ways of disposal are being considered:<br />

• utilization for irrigation;<br />

• utilization for bio-ponds;<br />

• filling of depressions or abandoned open cast;<br />

• filling of ponds for vaporizing.<br />

Analysis of degree of the air pollution with total emissions from UGCC and Akchalak CS has<br />

shown that in the area of design UGCC dwelling settlement and existing Akchalak settlement location<br />

maximum concentrations of contaminants in surface layer of the atmosphere will not exceed<br />

established MPCs.<br />

UGCC project implementation will undoubtedly negatively affect environmental complexes being<br />

close to it. In this respect all the technological decisions are to be directed to prevent those negative<br />

effects or minimize them as much as possible. On-site and off-site emissions sources will be equipped<br />

with appropriate analyzers to detect and control contaminants in the atmosphere. Carrying-out of<br />

monitoring will be based on the specially designed program specifying supervision network<br />

arrangement particularities, sampling periodicity, list of components to be control, character of route<br />

supervision as well as the content of reports with a glance at the technological peculiarities of the<br />

Project and relating estimated degree of influence upon the natural environment components.<br />

Book 5. Declaration of environmental impact concerning UGCC construction<br />

42