3. CLARIFICATION OF WORKS & PROCUREMENT MANUAL:<br />

Any executive seeking clarification of the Works and Procurement Manual will send mail<br />

furnishing, clause ref, page ref and the point on which clarification is sought to Chief<br />

Materials Manager (CMM), <strong>DVC</strong> Head Quarters. CMM should reply within 15 days of<br />

the receipt of the mail after obtaining clarification/interpretation from Chairman where ever<br />

required.<br />

4. PROCESSING OF INDENT & PLACEMENT OF ORDER:<br />

All Indents for procurement of materials including medicine and proposal for works (except civil)<br />

should be sent to respective Contract & Material department or Technical Section for processing<br />

and placement of order, after obtaining the approval of the competent authority as per concerned<br />

DFP. No other Department will place order to any Party. Where Technical section is not available,<br />

procurement functionaries will act as C & M department. All post tendering correspondence with<br />

the Vendors/ Contractors will be made by the respective Contract & Material (C&M) department<br />

only.<br />

For all meetings at scrutiny committee, QR Committee & Tender Committee, convener will<br />

be from the respective C&M department at concerned level.<br />

NOTE: In case of TAA is Board/ Chairman for placement of order, approval of member<br />

shall be obtained for any related activities unless specified otherwise.<br />

5. PROCEDURE FOR INDENTING:<br />

I INDENT:-<br />

(a) Indent will be raised, using the indent preparation screen/ format furnishing all particulars<br />

and submit the same for administrative approval. Indents for capital plant & machinery and<br />

other assets should be placed separately.<br />

(b) In case of works / service, proposal with scope of work to be placed to respective C & M<br />

backed by all information wherever available like last work order issued mode of tender, no.<br />

of techno-commercial acceptable offers, estimated cost along with basis, accepted rate etc.<br />

II. LAST PURCHASE PRICE/ WORK ORDER VALUE:-<br />

To prepare the estimate LPP may be considered on the following lines:<br />

i) The last purchase price (LPP) / last work order value will be the price paid in the<br />

latest contract of a similar magnitude, which is not more than three years old from the<br />

date of tender estimate. When similar item of same magnitude is not available, alternative<br />

methodologies may be resorted to.<br />

ii) Where the firm holding the LPP / last work order value contract has defaulted, the fact<br />

should be highlighted in the contract proposal and the price paid against the latest contract<br />

placed prior to the defaulting LPP / last work order value, where supplies / works<br />

have been completed, should be indicated but not more than three years old from the date of<br />

estimate.<br />

W& P Manual – 2012 Page 12