iii) Where the price indicated in the LPP / last work order value is subject to variation,<br />

besides indicating the original price of the LPP / last work order value, the updated<br />

price as computed in terms of the price variation clause, should also be indicated.<br />

iv) Where the supply/work order against the LPP / last work order value is yet to<br />

commence, i.e., delivery / completion schedule is not yet due, it should be indicated in the<br />

contract proposal, whether the contract holder is a past supplier/registered vendor/new vendor.<br />

In case of a new vendor, the price paid against the previous contract as in the case of (ii)<br />

above should be indicated.<br />

v) In the case of wholly imported stores, the comparison of the LPP should be made with the<br />

net C.I.F. value in foreign currency only.<br />

Indication of the percentage of increase over LPP/ last work order value should invariably be<br />

given in the contract proposals. For this purpose, a LPP / last work order value register will be<br />

maintained by all contract departments after sharing information among all the plants and HQ by<br />

sending copies of PO/WO for items/ works common to them.<br />

3.ESTIMATE :-<br />

As the estimated rate is a vital element in establishing the reasonableness of prices, it is important<br />

that the same is worked out in a realistic and objective manner on the basis of prevailing market<br />

rates, last purchase prices rate (not older than three years), economic indices (In absence of related<br />

indices, inflation @ 6% p. a or part there off. may be considered) for the raw material/labour (the same<br />

may be obtained from Labour Bureau, Shimla, RBI, or other Govt. published bulletin), other<br />

input costs, IEEMA formula, published data in paper/journals, wherever applicable and<br />

assessment based on intrinsic value etc. To take care of annual inflation last purchase rate if older<br />

than one year, @ 6% or change in related indices against basic material can be escalated per year.<br />

In case of preparation of estimate for AMC/ARC/one time job, due consideration should be given<br />

to the prevalent market rate for deployment of different category of workers/supervisors &<br />

engineers for the job based on minimum wages of Central govt. adopted by corporation.<br />

For civil works, latest published schedule rate of DSR has to be consulted. Items related to civil<br />

works of power plant reference of similar items of other organization like NTPC, BHEL & Govt.<br />

PSU may be referred if the item is not available in DSR.<br />

Budgetary offers from the reputed manufacturers for procurement may also be considered as a<br />

basis of estimate. Multiple budgetary quotations is preferable to be obtained and the 90% of<br />

lowest budgetary offer should be considered.<br />

Every indent for procurement must be forwarded with estimated cost along with the basis for the<br />

same, wherever possible.<br />

4. Indent should be forwarded through system by the Plant Chief/Chief Engineers to the Chief<br />