eyond the scheduled delivery period, LD to be imposed on the vendor for the portion of<br />

the delay attributable to him only. This is to be ascertained by the Indenting Officer.<br />

Paying authority should not deduct the L.D. amount directly as the reasons for delay<br />

is not fully known to them. On receipt of materials/execution of contracts after expiry of<br />

scheduled delivery period/time of completion as per the contract, the Paying authority<br />

should immediately clear the payment withholding (not deduction) the extent of<br />

L.D. amount as applicable and inform the order issuing authority and indenting officer<br />

/Engineer-in-Charge to resolve / settle the applicability of L.D. clause within a<br />

reasonable period, enclosing the Vendor’s appeal if any, thereafter the withheld L.D.<br />

amount to be regularized accordingly.<br />

However, request for any amendment for contract in respect of delivery / work<br />

completion schedule from the vendor/indenter to be made with specific reasons to the<br />

contract issuing authority within the tenure of scheduled delivery / completion period.<br />

Indenter / Inspecting Officer is requested to send a copy of inspection report as<br />

carried out as per terms of contract to the order issuing authority along with a copy of<br />

despatch clearance for the same.<br />

Purchase Order should stipulate that bill/invoice to be submitted by the supplier to the<br />

concerned Paying Authority (Accounts) directly along with all necessary documents (e.g.<br />

Test Certificate/Guarantee Certificate / Copy of ED Invoice, if applicable/copy<br />

of<br />

Despatch Clearance / copy of acceptance of SDBG, if any/copy of receipted challan for<br />

materials / documents against F&I Charge etc.) and should submit photocopy of the<br />

bill/invoice to the consignee at the time of delivery of requisite materials.<br />

Immediately on receipt of materials the consignee shall inform the indenter for necessary<br />

inspection (Zero day).<br />

After due inspection the indenter shall ensure that inspection report reaches to<br />

the consignee within 4 working days from zero day.<br />

On receipt of inspection report the consignee shall prepare the stores document (SRIN /<br />

SRB etc.) and ensure that the same along with inspection report and a photocopy of the<br />

invoice reaches to Accounts Office within 4 (four) working days for taking payment action<br />

by Accounts Department.<br />

Accounts Department thereafter shall release payment to the vendor as per Purchase<br />

Order within 7(seven) working days from the date of receipt of documents from Store<br />

Department.<br />

Similarly in case of Advance Payment against procurement of materials, the<br />

supplier shall submit the original Bills/Invoices to the concerned Accounts Office with all<br />

relevant documents as per purchase order and photocopy of invoices to be submitted to<br />

the consignee. The consignee in turn shall issue necessary payment clearance to<br />

Accounts in consultation with indenter within 3 (three) working days. Thereafter<br />

Accounts will release the advance payment within 2 (two) working days of receipt<br />

of payment clearance from the consignee.<br />

W& P Manual – 2012 Page 79