Payment against dispatch documents:<br />

Evidence of despatch (R/R or receipted<br />

LR).<br />

Detailed invoice and detailed packing list identifying content of each<br />

consignment. Manufacturer’s/contractor’s guarantee certificate of quality.<br />

Test certificate.<br />

Material inspection report and/or despatch clearance<br />

certificate. Insurance policy/certificate.<br />

A.3 Payment against consignment after receipt of material at site<br />

A.3.1 Certificate to be issued by Site-in-charge :<br />

a) Physically verified and materials found to be received in full and good<br />

condition. b) Materials entered in page no… Vol. …. of stock ledger.<br />

A.3.2 CRMI issued with cross-reference of stock<br />

ledger. A.4 Retention money:<br />

Recovery towards LD, if any.<br />

Successful commissioning and taking over certificate.<br />

Certification towards submission of all drawings, manuals, reproducible etc.<br />

A.5 Erection Payment :<br />

The existing procedure of payment through RA bill after entering the work done in<br />

the measurement book (MB) will continue to remain in vogue.<br />

N.B.<br />

1) In case of delayed execution of work, payment against running bill (both supply<br />

and erection) will not be withheld for want of Provisional/formal extension order.<br />

2) EFP compliance certificate will normally be furnished in the succeeding month(s)<br />

and shall not be delayed beyond 6 (six) months.<br />

3) For minor discrepancies, entire payment will not be withheld.<br />

In order to release payment to contractor within 15 (fifteen) days from the date of<br />

submission of bill in regard to work relating to Project Contract on EPC/Turnkey<br />

basis with stage wise payment terms with immediate effect. For adhering to the above<br />

schedule, the following procedure and time frame shall be followed:<br />

Bill for stage payment to be submitted by the contractor in quadruplicate with all<br />

relevant document to Engineer/in/Charge directly.<br />

Engineer-in-Charge on receipt of the bill will forward the same to the concerned site<br />

engineer for necessary verification and certification in respect of completion of the stages of the<br />

work for which the bill has been preferred and also sent one copy to EPF cell for verifications<br />

and certification of EPF declaration submitted by the Contractor (zero date).<br />