M-5 and M2-M4 where TAA is minimum Director and below Director (upto EE/SDE level)<br />
level respectively. The observation report of the scrutiny committee will be placed by dealing<br />
officers of respective C&M department to appropriate TC for their review and<br />
recommendation. The said committee will be formed at the time of formation of TC.<br />
The scopes of the committee are as follows :-<br />
i)To verify the information mentioned in the comparative statement on their related fields.<br />
ii) Scrutiny of techno-commercial part by concerned representative like indenting<br />
representative will check the technical part. C&M representative will check the<br />
commercial part and finance representative will check the finance part respectively.<br />
iii) Certification on NIT compliance.<br />
iv) To prepare a deviation statement category wise i.e. must conditions and others<br />
conditions, if any.<br />
v) Identification of L-1 bidder.<br />
The said report may assist the decision making process of TC.<br />
Note: Name of the scrutiny committee member may be collected from respective department<br />
over phone by TIA to speedy disposal and same to be regularised through noting before<br />
submission of scrutiny committee report to TC.<br />
3. In case of approving authority being Board/Chairman /Directors/ Member (T) in respect of a<br />
proposal initiated from a project, such proposal is to be initially evaluated by the level of<br />
committee as mention at column-4 at the respective project and to be sent to concerned<br />
Director, HQ along with the recommendation of project/ construction head for further evaluation<br />
by respective level of committee as mention in column 3 at HQ before placing such proposal<br />
for approval.<br />
4. All proposals for approval required at a level higher than Member(Technical) in respect of<br />
cases shall be recommended by Member (Technical) with the con currence of Member<br />
(Finance).<br />
5. Where requisite level of officers is not available, in that case higher level officers will be<br />
nominated in the committee.<br />
6. Where requisite level of officers is not available for recommendation of name in TC committee,<br />
TIA may nominate the same.<br />
7. In case of DFP(OE), TC will represent by minimum M-5 and M-4 officers where approving<br />
authority is HOD and HOO respectively.<br />
Representative of C&M deptt will be the nodal agency to put up the proposal for formation of<br />
T.C. The tender Committee will be formed and approved by the respective Approving Authority<br />
prior opening of the tender bids.<br />
31. SCOPE OF WORK OF TC:<br />
Function of TC will commence after opening of tender. The scope of work of TC should be to<br />
scrutinize the tenders received to find out whether these are complete in all respects and binding<br />
on the tenderers. The committee will also check all the information related to credentials &<br />
techno-commercial as submitted by the bidders as per NIT stipulated. TC also record on the<br />
W& P Manual – 2012 Page 61