(VERSION-IV) - DVC :: Consumer Login
(VERSION-IV) - DVC :: Consumer Login
(VERSION-IV) - DVC :: Consumer Login
- No tags were found...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
38. DEL<strong>IV</strong>ERY PERIOD CONSIDERATION:<br />
No weightage should be given for early delivery of goods/early completion of works than that<br />
mentioned in the NIT. In case any bidder offers belated delivery/ completion schedule for 2-part<br />
bid, there may be option to pursue the bidder to match the delivery clause/ completion schedule of<br />
NIT, provided same has not been declared in deviation schedule by the bidder. Date of delivery is<br />
to be reckoned as the date of receipt of materials/goods by the consignee. However In case of exworks<br />
basis, the delivery date will be considered as per date of date of consignment note.<br />
39. LIQUIDATED DAMAGE:<br />
The time remains the essence of all major contracts / purchase orders awarded by <strong>DVC</strong> and all<br />
deliverables under a Purchase Order / Work Order needs to be completed within the contractual<br />
time schedule. Therefore, the provision has been kept in the contract/Purchase Order that in case<br />
of delay in completion, for the reasons attributable to the contractor, Purchaser/owner reserves the<br />
right to recover from the Vendor a sum equivalent to 0.5% of the value of the delayed materials /<br />
work / equipment / spares for each week of delay and part thereof subject to maximum of 5% of<br />
the total value of the contract as Liquidated Damage (LD).<br />
LD is to be ascertained by the Indenting Officer.<br />
In the event of any difficulty in deciding on the imposition of LD at the intermediate stages<br />
(specially in works/turnkey contracts) during execution of any contract provisional time extension<br />
may be granted with the approval of the competent authority as per delegation so that there is no<br />
problem in accepting delayed supply/works. Such provisional time extension shall be without<br />
prejudice to the right of <strong>DVC</strong> in levying LD and other rights as per terms of the contract.<br />
However, there shall be no restriction in issuing final extension order at any stage of the work<br />
wherever it is possible to do so.<br />
In cases, where the works/supply/services extend beyond the contractual completion<br />
schedule/delivery period and provisional extension order is issued without deciding on the<br />
application of LD, no amount from the RA bill will be withheld in case where adequate retention<br />
payment (over and above SD) remains with <strong>DVC</strong> as per terms of the contract (10% payment is<br />
retained against supply and erection for turnkey contracts). In absence of such retention,<br />
admissible LD amount as decided by concerned Chief Engineer shall be withheld from their<br />
running bill till final decision on LD is taken.<br />
Paying authority should not deduct the L.D. amount directly as the reasons for delay is not fully<br />
known to them. On receipt of materials/execution of contracts after expiry of scheduled delivery<br />
period/time of completion as per the contract, the Paying Authority should immediately clear the<br />
payment without waiting for formal delivery period / time extension order, withholding (not<br />
deduction) the extent of L.D. amount as applicable and inform the order issuing authority and<br />
indenting officer to resolve/settle the applicability of L.D. clause within a reasonable period<br />
enclosing the Vendor’s appeal if any, thereafter the withheld L.D. amount to be regularized<br />
accordingly.<br />
W& P Manual – 2012 Page 66