The payment of advance is normally discouraged. The advance payment, in exceptional cases,<br />

may be given to the extent of 10% of total ordered value against submission of a Bank Guarantee<br />

of equivalent amount (on account of advance) and the same should have sufficient validity<br />

covering the full delivery period / full completion period and final payment thereof. Rate of<br />

interest of advance should be package specific and commensurate with the market rate.<br />

PAYMENT THROUGH RTGS/NEFT<br />

All payments to the vendors will be released through RTGS/EFT only.<br />

Vendors are requested to submit the requisite details as per Annexure E.<br />

The contractor/vendor shall furnish the following certificate to the Paying Authority along with<br />

each invoice/bill against payment for supplies made against any supply order/RC with longer<br />

completion period (more than a year), if the same is placed on firm price basis. ‘I / we certify that<br />

there has been no reduction in the sale price of the stores of description identical to this item,<br />

supplied to any person/organization and such stores have not been offered/sold by me/us to any<br />

person/organization at a price lower than the price charged under this contract upto the date of<br />

this bill.’<br />

20. ADDITIONS / ALTERATIONS / MODIFICATIONS :<br />

The Owner reserves the right to make additions/reduction/ alterations/ modifications to the<br />

quantity of the items in the Purchase Order. The Vendor shall supply such quantities also at the<br />

same rate as originally agreed to and incorporated in the Purchase Order. If, however, the<br />

additional supply is at variance with design, size and specifications and not already covered by<br />

the Purchase Order or the amendments therein, the rates for such additional supply shall be<br />

negotiated and mutually agreed upon.<br />

21. DEL<strong>IV</strong>ERY SCHEDULE / COMPLETION PERIOD :<br />

Time is the essence of this contract and normally no variation shall be permitted in the<br />

completion time/delivery schedule mentioned in the Order/contract unless an amendment in this<br />

regard is issued by <strong>DVC</strong>. Time extension may be issued on specific request/reason provided such<br />

request is communicated to the Order Issuing Authority before the expiry of the stipulated<br />

delivery schedule/completion period. Date of delivery of materials/goods is to be reckoned as the<br />

date of receipt of same by the consignee.<br />

22. LIQUIDATED DAMAGES FOR DELAY IN DEL<strong>IV</strong>ERY /COMPLETION OF<br />

WORKS:<br />

22.1 The time remains the essence of any contract/ purchase order awarded by <strong>DVC</strong> and all<br />

supply under a Purchase Order/all deliverables under a Work Order needs to be completed within<br />

the stipulated time schedule.<br />

The Contractor shall commence work on the Facilities from the date of Notification of Award.<br />

The Contractor shall thereafter proceed with the Facilities in accordance with the time schedule<br />

specified in Time Schedule to the Contract Agreement.<br />

Therefore, the provision has been kept in the contract that in case of delay in completion/delivery,<br />

for the reasons attributable to the contractor/ vendor, owner reserves the right to recover from the<br />