2.5<br />

c) The Contractor shall get all his Lifting equipments and tackles thoroughly<br />

examined / tested through a Competent Persons, approved by the local state<br />

government, where the work is being undertaken.<br />

d) Before Start of work by the Contractor, the Contractor shall present his Personal<br />

Protective equipments to Head of <strong>DVC</strong> Safety Deptt, and Engineer In charge, for<br />

inspection, who will inspect these equipments for necessary legal compliance. Only<br />

after this inspection and clearance in writing, above referred items shall be used or<br />

issued by the Contractor.<br />

e) Before using the lifting equipments and other safety related items, the contractor<br />

shall present these to Head of <strong>DVC</strong> Safety Deptt, and Engineer In charge, for<br />

inspection, who will inspect these equipments for its safety. Only after their<br />

clearance in writing, these items shall be used by the Contractor. However, all<br />

liabilities for statutory violations for these equipment shall be of the Contractor.<br />

Before Start of the contract, the Contractor shall provide appropriate Safety<br />

Training to all his workers of at least one full day duration, through an external<br />

agency, with faculty having the qualification as mentioned in the Factories Act/<br />

State Rules for the Safety Officer, and having minimum 5 years of power plant site<br />

exposure, with regard to implementing safety provisions.. Only those who are<br />

trained, as above, shall be allowed for issue of Gate Pass.<br />

f) Before Start of work by the Contractor, the Contractor shall get occupational<br />

health examination of his workers, working/ to work in hazardous activities<br />

through a Medical Practitioner, approved by the State Government, and<br />

subsequently as mentioned in the state factories rules.<br />

g) In case any accident occurs and <strong>DVC</strong> Officials investigate it, the Contractor<br />

shall provide full cooperation in conduct of inquiry, conducted by the <strong>DVC</strong><br />

officials, in case of any accident at his workplace or to his worker.<br />

e) Wherever there is probability of fall of worker/ material from more than 8 Ft, to<br />

prevent his fall, the contractor shall provide Safety Harness to all his workers and<br />

ensure its use. He shall also provide safety net below such work place. He shall<br />

ensure compliance of all provisions of Permit for working at height devised by<br />

<strong>DVC</strong>. If the fall arrester is provided by <strong>DVC</strong>, the Contractor shall ensure its right<br />

use.<br />

The contractor shall use only double insulated power tools shall be used at the<br />

construction place. He shall only use 3 Core cable for Single phase Supply and 4<br />

Core Cable for 3 Phase supply. For all electrical connections appropriate ELCB<br />

shall be used by the Contractor.<br />

a) In no case any electric supply shall be taken through loose wire like supply<br />

without Plug Top.<br />