EPF cell with check and certify the EPF declaration within 5(five) working days from the<br />

zero date and return the same to Engineer-in-Charge.<br />

The concerned site Engineer will check and certify on the bill within 7(seven) working<br />

days from the zero date.<br />

On receipt of the verified bill, Engineer-in-Charge shall ensure that the pass order along with<br />

the bill and other relevant documents reaches to Accounts Office within 3(three) working days<br />

for taking payment action by Accounts Department.<br />

Accounts Department shall release payment to the contractor as per terms and conditions<br />

of<br />

Work Order/Contract within 5(five) working days.<br />

In case of advance payment, the contractor shall submit the bill to the Engineer-in-Charge<br />

with all relevant documents as per work order including SDBG and BG of equivalent amount of<br />

advance. The Engineer-in-Charge in turn shall issue necessary payment clearance to Account<br />

Department after acceptance of SDBG and BG against advance within 3(three) working days.<br />

Thereafter, Accounts will release the advance payment within 2(two) working days of receipt of<br />

payment clearance from the Engineer-in-Charge.<br />

In case of delayed execution of work, Accounts Office should pass the bill<br />

withholding admissible Liquidated Damage (LD) amount as per the Work Order/Contract<br />

without waiting for format time extension order except where the extension of time has already<br />

been granted for non-imposition of LD by the Competent Authority. Thereafter, Accounts<br />

Officer should immediately intimate the Engineer-in-Charge for issuance of format extension of<br />

time with/without imposition of LD Clause.<br />

Accounts Department should prepare a monthly report of the overdue bills at the end of<br />

each month due to non-receipt of documents, clarification require indicating details thereof and<br />

to be submitted to concerned Project Head with copies thereof to Member (Finance).<br />

However, the above payment procedure will not be applicable for item rate contract and<br />

the existing system in this regard will continue.<br />

N.B: EPF compliance certificate will normally be furnished in the succeeding month.<br />

However, in no case, the compliance shall be delayed beyond 6(six) months.<br />

53. TOLERANCE IN PURCHASE ORDER<br />

QUANTITY:<br />

The suppliers are expected to deliver exact quantities of material as specified in the Purchase<br />

Order/turnkey contracts. But wherever quantities are in Weights, volumes or in lengths, there may<br />

be cases where the supplier has made supplies in excess or short. If any tolerance has not been<br />

incorporated in the Purchase Order/work order/turnkey contract then ± 5% of the order<br />

value should be considered as the tolerance limit and the Purchase Order/work order/turnkey<br />

contract shall automatically be treated as amended to that extent.<br />

54. PRE-DISPATCH INSPECTION (PDI), RECEIPT OF MATERIAL,<br />

ETC:<br />

PDI Clause for a particular tender/enquiry to be incorporated, if felt necessary, by the indenter.<br />

W& P Manual – 2012 Page 82