EPF cell with check and certify the EPF declaration within 5(five) working days from the<br />
zero date and return the same to Engineer-in-Charge.<br />
The concerned site Engineer will check and certify on the bill within 7(seven) working<br />
days from the zero date.<br />
On receipt of the verified bill, Engineer-in-Charge shall ensure that the pass order along with<br />
the bill and other relevant documents reaches to Accounts Office within 3(three) working days<br />
for taking payment action by Accounts Department.<br />
Accounts Department shall release payment to the contractor as per terms and conditions<br />
of<br />
Work Order/Contract within 5(five) working days.<br />
In case of advance payment, the contractor shall submit the bill to the Engineer-in-Charge<br />
with all relevant documents as per work order including SDBG and BG of equivalent amount of<br />
advance. The Engineer-in-Charge in turn shall issue necessary payment clearance to Account<br />
Department after acceptance of SDBG and BG against advance within 3(three) working days.<br />
Thereafter, Accounts will release the advance payment within 2(two) working days of receipt of<br />
payment clearance from the Engineer-in-Charge.<br />
In case of delayed execution of work, Accounts Office should pass the bill<br />
withholding admissible Liquidated Damage (LD) amount as per the Work Order/Contract<br />
without waiting for format time extension order except where the extension of time has already<br />
been granted for non-imposition of LD by the Competent Authority. Thereafter, Accounts<br />
Officer should immediately intimate the Engineer-in-Charge for issuance of format extension of<br />
time with/without imposition of LD Clause.<br />
Accounts Department should prepare a monthly report of the overdue bills at the end of<br />
each month due to non-receipt of documents, clarification require indicating details thereof and<br />
to be submitted to concerned Project Head with copies thereof to Member (Finance).<br />
However, the above payment procedure will not be applicable for item rate contract and<br />
the existing system in this regard will continue.<br />
N.B: EPF compliance certificate will normally be furnished in the succeeding month.<br />
However, in no case, the compliance shall be delayed beyond 6(six) months.<br />
53. TOLERANCE IN PURCHASE ORDER<br />
QUANTITY:<br />
The suppliers are expected to deliver exact quantities of material as specified in the Purchase<br />
Order/turnkey contracts. But wherever quantities are in Weights, volumes or in lengths, there may<br />
be cases where the supplier has made supplies in excess or short. If any tolerance has not been<br />
incorporated in the Purchase Order/work order/turnkey contract then ± 5% of the order<br />
value should be considered as the tolerance limit and the Purchase Order/work order/turnkey<br />
contract shall automatically be treated as amended to that extent.<br />
54. PRE-DISPATCH INSPECTION (PDI), RECEIPT OF MATERIAL,<br />
ETC:<br />
PDI Clause for a particular tender/enquiry to be incorporated, if felt necessary, by the indenter.<br />
W& P Manual – 2012 Page 82