Once it is incorporated in the purchase order/contract, it should not be waived in the<br />
normal course by way of amendment. However in case of extreme exigencies, PDI can be<br />
waived by the Chief Engineer on the basis of appropriate justification by the order issuing<br />
Authority.<br />
If a PO/LOI/LOA incorporates PDI, Inspection Engineer will carry out the relevant<br />
tests/inspection as per relevant standard at vendor’s works. After successful testing/inspection,<br />
despatch clearance is to be issued by the Inspecting Engineer as per format incorporated in this<br />
manual. For this purpose, Inspection Engineer may contact his superior over telephone/fax, if<br />
needed for issuance of despatch clearance.<br />
Before proceeding for inspection at vendor’s works, the Inspection Engineer should contact the<br />
vendor with the help of consignee via phone/fax to know the exact number of way<br />
bills/road permit required to despatch the materials. Consignee should hand over the required<br />
number of road permits/way bills to the Inspection Engineer before he leaves for PDI. The<br />
Inspector should hand over the way bills/Road Permits to the vendor along with dispatch<br />
clearance. Responsibility for providing the requisite number of road permits/way bills to the<br />
Inspection Engineer before leaving for inspection lies with the concerned consignee.<br />
Paying Authority should not insist for extension of submitted BG, if needed, due to late receipt of<br />
the materials /delayed completion of works. The same should be taken care of by the<br />
Order Issuing Authority within the validity period of the submitted BG.<br />
Where PDI Clause has not been incorporated in the PO/contract, consignee would send the Road<br />
Permit/ Way Bill as per the written request of the vendor. He would check the mode of<br />
despatch and the Insurance Cover being taken. After receipt of the materials at stores,<br />
consignee will arrange for site inspection by calling the Indenting Officer by sending an arrival<br />
report.<br />
Consignee would send all the relevant documents to the concerned Accounts Office for checking,<br />
verifying and passing of the bills for payments to the vendor. The Accounts Office would see<br />
all the relevant documents and in case of discrepancy found as per Purchase Order/work order<br />
shall seek clarification before releasing the payment. Consignee/ Indenter would also send the<br />
copies of site inspection reports/PDI reports to the purchase order issuing authority.<br />
55. PAYMENT<br />
TERM:<br />
a) General payment<br />
term:-<br />
The normal payment term of <strong>DVC</strong> for supply order is ‘100% payment with full taxes &<br />
duties will be made within 15 working days of receipt of material at site and inspection &<br />
acceptance thereof’ or within 15 (fifteen) working days of submission of invoice<br />
whichever is later. However, payment terms for POs placed directly on manufacturer may also<br />
be done as below:<br />
90% of the ordered value to be paid against despatch documents through bank subject to<br />
acceptance of SDBG, if applicable. Balance 10% of the ordered value to be paid after receipt of<br />
materials at site and acceptance thereof.<br />
W& P Manual – 2012 Page 83