EIA for the proposed Hulhule-Male’ Bridge Project<br />

Air-borne dust from material mixing<br />

The concrete mixing stations is set up in three construction sites for the project. Among these,<br />

the surrounding precast yard in Hulhumale’ and the construction site in Hulhule’ had no<br />

residential area, hence mixing station will have no effect. In contrast, the mixing station in the<br />

construction site in Male’ is in close proximity to residential buildings; hence the impact on<br />

these residences will be high unless mitigation measures are taken. Thus, all mixing stations will<br />

adopt concentrated mixing mode and will operate in a fully enclosed space, to minimise the<br />

impact of air-borne dust in mixing process and to control the air-borne dust pollution from<br />

mixing materials.<br />

In conclusion, the air-borne dust pollution during the construction period of the project is mainly<br />

from the road construction dust, the pipeline construction dust, construction air-borne dust in<br />

storage yards and from mixing materials. Strict pollution control plans and precautionary<br />

measures in accordance with the relevant laws and regulations will need to be executed to<br />

effectively control and alleviate air-borne dust pollution.<br />

6.6.1.2 Mitigation measures<br />

Specific measures about prevention and control of dust pollution are as follows:<br />

• Fixed hard enclosure walls not lower than 2 m high will be set up around the construction<br />

area of the proposed project to prevent the impact of air-borne dust in the construction<br />

site; the contractor will assure that trained staff will be responsible for the maintenance<br />

and repair of facilities and for regular inspections.<br />

• Optimize the layout plan of construction site in Male: the concrete mixing area where the<br />

air-borne dust is produced will be arranged on the eastern side, away from residential<br />

area.<br />

• When the construction machineries are at work in the construction process of roadbed,<br />

pipelines, etc., the surface should be regularly watered to prevent air-borne dust<br />

pollution.<br />

• Facilities to wash vehicles, matched drainage facilities and mud sedimentation facilities<br />

will be set up at the construction site. The carrier vehicles will be washed, covered and<br />

cleaned thoroughly daily. This will prevent the construction materials, rubble and muck<br />

from scattering.<br />

• The road used to transport materials and the road in and out of the storage yard will be<br />

watered timely. The contractor will provide watering carts for watering twice a day and<br />

watering number should be appropriately increased in humid weather or strongly windy<br />

weather to prevent air-borne dust on the pavements.<br />

Prepared by: CDE Consulting & China Shipping Environment Technology<br />