EIA for the proposed Hulhule-Male’ Bridge Project<br />

• Daily inspection of site clearance activities to ensure that the proposed construction plans<br />

are followed.<br />

• Weekly assessment to determine that toilets are in proper working order. This will ensure<br />

that sewage disposal will be adequately treated.<br />

• Monitor and ensure that approved suppliers and sources of local materials are used,<br />

where practical.<br />

9.5 Monitoring during operations phase<br />

Table 9.3 shows the details of the different monitoring attributes and parameters must be<br />

monitored during the operations stage.<br />

The purpose of these assessments are to identify the potential negative effects of the bridge<br />

operations such as emissions, water runoff, marine ecological changes, traffic accidents and<br />

provide guidance to undertake corrective measures.<br />

9.6 Socio-economic impact monitoring<br />

Table 9.4 shows the details of the socio-economic impact monitoring matrix.<br />

9.7 Monitoring Report<br />

A detailed environmental monitoring report is required to be compiled and submitted to the EPA<br />

annually based on the data collected for monitoring the parameters included in the monitoring<br />

plan given in the EIA. This report may be submitted to the relevant Government agencies in<br />

order to demonstrate compliance. If required, however, a monitoring report for the proposed<br />

work phase may be prepared and submitted to the Ministry of Environment. The report will<br />

include details of the site, strategy of data collection and analysis, quality control measures,<br />

sampling frequency and monitoring analysis and details of methodologies and protocols<br />

followed. In addition to this more frequent reporting of environmental monitoring will be<br />

communicated among the environmental consultant, project proponent, the contractors and<br />

supervisors to ensure possible negative impacts are mitigated appropriately during and after the<br />

project.<br />

9.8 Commitment for Monitoring<br />

The proponent is fully committed to undertake the monitoring program outlined in this Chapter<br />

(refer Appendix L of this report).<br />

Prepared by: CDE Consulting & China Shipping Environment Technology<br />