EIA for the proposed Hulhule-Male’ Bridge Project<br />

2 <strong>PROJECT</strong> DESCRIPTION<br />

2.1 Project Location<br />

The project location is Gaadhoo Koa, the reef pass between Hulhule and Male’ Island (see<br />

Figure 2.1). The widths of the channel along the proposed survey lines cover about 1400 m. The<br />

proposed landing area for the Male’ side is at the SE corner of the island where<br />

Boduthakurufaanu Magu meets the Tsunami Monument. The landing area on Hulhule’ side is at<br />

the southern tip of the island. An area is planned to be reclaimed and protected with a breakwater<br />

to facilitate the landing area. The road on Male’ side connects to Boduthakurufaanu Magu and<br />

changes are proposed to the road layout in nearby streets.<br />

The landing site on Hulhule site will connect with the causeway and road connecting Hulhule<br />

and Hulhumale’ Island.<br />

The work site on Male’ is located at the “Adi Park”. Site in Hulhule and Hulhumale’ is located<br />

on newly reclaimed barren land. A borrow areas has been identified on Gulhifalhu Island (See<br />

Figure 2.1)<br />

There are no major protected areas within close proximity to the bridge site (See Figure 2.2) but<br />

there is an important dive site within 500m of the bridge.<br />

2.2 Project Outline and Project Site Plan<br />

The proposed site plan is presented in Appendix B. As noted above the project involves<br />

constructing a bridge between Hulhule and Male’. Figure 2.3 shows a reduced version of the site<br />

plan and Figure 2.4 provides the project footprint and potential affected area.<br />

The overall distance covered by the project including the landing area roads is 2.0 km long. The<br />

length of the bridge including the approaches is 1.390 km and the width is 20.3 m. The height of<br />

the bridge from MSL is 20 m.<br />

The main bridge is a prestressed concrete six-span continuous rigid frame structure. The main<br />

bridge is 760 m long. The approach bridge is pre-stressed concrete I-type beam bridge and is 630<br />

m long.<br />

The main components of the project are:<br />

• Mobilization and work site setup (in Male’, Hulhule and Hulhumale’)<br />

• Land reclamation and shore protection at Hulhumale’ landing site<br />

Prepared by: CDE Consulting & China Shipping Environment Technology<br />