EIA for the proposed Hulhule-Male’ Bridge Project<br />

sedimentation treatment in the sedimentation tank, and the final<br />

wastewater along with sewage from the septic tanks shall be transported<br />

together to the designated waste management centre in Thilafushi.<br />

Chemicals and hazardous materials used on the vessel shall be safely<br />

stored and secured. The sandstone, cement and other powdery materials<br />

stockpiled on the construction trestle, temporarily-constructed dock and<br />

concrete mixing vessel must be covered for safekeeping.<br />

During the construction phase, all machineries and vessels must be<br />

inspected strictly, so as to prevent oil spills. Oil spill kits shall be made<br />

readily available on site to handle any accidental spills.<br />

Disposal of any sewage, garbage and waste oil to the sea is strictly<br />

forbidden. Such waste should be gathered and disposed together with<br />

other pollutants on the bridge construction site.<br />

Prior to construction commencement, the detailed investigation shall be<br />

completed for the sea bed along the bridge pier construction area. Any<br />

live coral along the area and within 10m scope of its periphery should be<br />

transplanted.<br />

All operations shall be handled by experienced personnel and supervised<br />

thoroughly.<br />

Terrestrial flora and<br />

fauna management<br />

Any trees impacted by works along the land connection and parallel<br />

crossing on Male Island, shall be transplanted as per relevant local laws<br />

and regulations. Therein, there is an old Nika tree (Ficus benghalensis)<br />

on Moonlight Higun which falls in the vicinity of the land area<br />

connection plans of Male island for this project. Removal of this tree<br />

should be avoided as much as possible, and unless absolutely necessary,<br />

Project proponent<br />

Continuous, during<br />

construction phase<br />

Prepared by: CDE Consulting & China Shipping Environment Technology<br />

Page|220