EIA for the proposed Hulhule-Male’ Bridge Project<br />

2.3 Detailed Project Outline<br />

2.3.1 Bridge Design Considerations<br />

2.3.1.1 Traffic Forecasts<br />

The planned traffic volume for this project is presented in Table 2.1.<br />

Table 2.1: Predicted Results on Traffic Volume for this Project (pcu/d)<br />

Year 2018 2024 2032<br />

Equivalent of automobile 3314 5925 7218<br />

Therein:Bus 285 536 658<br />

Motorcycle 5465 9598 11818<br />

2.3.1.2 Major technical standards<br />

• Road grade: first-class highway<br />

• Designed driving speed: 60 km/h<br />

• Bridge’s normal width: 20.3 m; for specific road width, refer to Figure 2.5<br />

• Design load of bridge: highway – Grade I<br />

• Deck transverse slope: 2.5%<br />

• Design tide level: design highest tide level: 0.55 m, design lowest tide level: -0.51 m<br />

• Design standard wind speed: 26.3 m/s<br />

• Seismic peak ground acceleration: 43 gal, Grade VI<br />

Figure 2.5 Typical Cross-section of the Bridge<br />

2.3.1.3 Plane design<br />

This project starts from the southeast corner of Malé, links up with the planned<br />

Boduthakurufaanu Magu (road), and then connects to the Moonlight Hin’gun road by setting a<br />

grade crossing at AK0+036. The Male’ side approach bridge starts around the tsunami<br />

Prepared by: CDE Consulting & China Shipping Environment Technology Page| 18