EIA for the proposed Hulhule-Male’ Bridge Project<br />

Landing in Male’ will be via the barge landing area next to Viligilli ferry terminal.<br />

2.4.5 Construction method of breakwater<br />

Breakwater will be constructed using excavators and loaders. The use of cranes may be less<br />

practical given the frequent disruptions anticipated during flight take-off and landing. The core<br />

of the breakwater will be constricted from geobags filled with sand. The upper layers will be<br />

filled with filter cloth and layers of rubble for cushioning. The main breakwater units will be<br />

quadrangle hollow blocks constructed from concrete. These units will be manufactured on the<br />

Hulhule worksite or the pre-casting yard at Hulhumale’ and transported to the site on a need<br />

basis.<br />

2.4.6 Equipment<br />

Key equipment of the main bridge, approach bridge, girder precast & installation and land<br />

connection works are presented in Table 2.3, Table 2.4, Table 2.5, Table 2.6.<br />

Table 2.3 Key equipment for the main bridge<br />

S/N Equipment name Power or tonnage Qty. Remarks<br />

1 Floating crane of 350 t 350 t 1<br />

2 Floating crane of 100 t 350 t 1<br />

3 Concrete mixing vessel 160 m³/h 2<br />

4 Crawler crane 200 t(150 t) 1 Pile casting down-pass<br />

5<br />

Abrasion drill or spin dig<br />

drill<br />

Φ 250 cm 12 Bored pile construction<br />

6 Hanging baskets 200 t 10 sets<br />

Table 2.4 Key equipment for the approach bridge<br />

S/N Equipment name Capability Qty. Use<br />

1<br />

Set up drilling platforms and<br />

Self-elevating Water depth >10 m<br />

3 construction of the bored piles<br />

mobile platform ,loads 200 t<br />

for five months<br />

2 Crawler crane 80 t 3<br />

Pass down the pile casing for<br />

five months<br />

3<br />

Abrasion drill or<br />

rotary drill<br />

φ160 cm 6 Pile casing rock-socketed<br />

4 Trestle 1 300×8=2400 m 2 1 Male island side<br />

Prepared by: CDE Consulting & China Shipping Environment Technology Page| 33