08.01.2017 Views

3e2a1b56-dafb-454d-87ad-86adea3e7b86

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Chapter 6 Supply network design 159<br />

Worked example<br />

A business process outsourcing (BPO) company is considering building some processing<br />

centres in India. The company has a standard call centre design that it has found<br />

to be the most efficient around the world. Demand forecasts indicate that there is<br />

already demand from potential clients to fully utilize one process centre that would<br />

generate $10 million of business per quarter (3-month period). The forecasts also<br />

indicate that by quarter 6 there will be sufficient demand to fully utilize one further processing<br />

centre. The costs of running a single centre are estimated to be $5 million per<br />

quarter and the lead time between ordering a centre and it being fully operational is<br />

two quarters. The capital costs of building a centre is $10 million, $5 million of which<br />

is payable before the end of the first quarter after ordering, and $5 million payable<br />

before the end of the second quarter after ordering. How much funding will the company<br />

have to secure on a quarter-by-quarter basis if it decides to build one processing<br />

centre as soon as possible and a second processing centre to be operational by the<br />

beginning of quarter 6?<br />

Analysis<br />

The funding required for a capacity expansion such as this can be derived by calculating<br />

the amount of cash coming in to the operation each time period, then subtracting<br />

the operating and capital costs for the project each time period. The cumulative cash<br />

flow indicates the funding required for the project. In Table 6.6 these calculations are<br />

performed for eight quarters. For the first two quarters there is a net cash outflow<br />

because capital costs are incurred by no revenue is being earned. After that, revenue is<br />

being earned but in quarters four and five this is partly offset by further capital costs for<br />

the second processing centre. However, from quarter six onwards the additional revenue<br />

from the second processing centre brings the cash flow positive again. The maximum<br />

funding required occurs in quarter two and is $10 million.<br />

Table 6.6 The cumulative cash flow indicating the funding required for the project<br />

Quarters<br />

1 2 3 4 5 6 7 7<br />

Sales revenue ($ millions) 0 0 10 10 10 20 20 20<br />

Operating costs ($ millions) 0 0 −5 −5 −5 −10 −10 −10<br />

Capital costs ($ millions) −5 −5 −0 −5 −5 0 0 0<br />

Required cumulative funding ($ millions) −5 −10 −5 −5 −5 +5 +15 +25<br />

Break-even analysis of capacity expansion<br />

Fixed-cost breaks are<br />

important in determining<br />

break-even points<br />

An alternative view of capacity expansion can be gained by examining the cost implications<br />

of adding increments of capacity on a break-even basis. Figure 6.11 shows how increasing<br />

capacity can move an operation from profitability to loss. Each additional unit of capacity results<br />

in a fixed-cost break that is a further lump of expenditure which will have to be incurred<br />

before any further activity can be undertaken in the operation. The operation is unlikely<br />

to be profitable at very low levels of output. Eventually, assuming that prices are greater<br />

than marginal costs, revenue will exceed total costs. However, the level of profitability at the<br />

point where the output level is equal to the capacity of the operation may not be sufficient<br />

to absorb all the extra fixed costs of a further increment in capacity. This could make the<br />

operation unprofitable in some stages of its expansion.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!