08.01.2017 Views

3e2a1b56-dafb-454d-87ad-86adea3e7b86

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

470<br />

Part Three<br />

Planning and control<br />

Critical commentary<br />

When project managers talk of ‘time estimates’, they are really talking about guessing.<br />

By definition, planning a project happens in advance of the project itself. Therefore, no<br />

one really knows how long each activity will take. Of course, some kind of guess is needed<br />

for planning purposes. However, some project managers believe that too much faith is<br />

put in time estimates. The really important question, they claim, is not how long will something<br />

take, but how long could something take without delaying the whole project. (We<br />

deal with this issue partially when we discuss the concept of float later in the chapter.)<br />

Also, if a single most likely time estimate is difficult to estimate, then using three, as one<br />

does for probabilistic estimates, is merely over-analysing what are highly dubious data<br />

in the first place.<br />

Identify relationships and dependencies<br />

All the activities which are identified as composing a project will have some relationship with<br />

one another that will depend on the logic of the project. Some activities will, by necessity,<br />

need to be executed in a particular order. For example, in the construction of a house, the<br />

foundations must be prepared before the walls are built, which in turn must be completed<br />

before the roof is put in place. These activities have a dependent or series relationship. Other<br />

activities do not have any such dependence on each other. The rear garden of the house could<br />

probably be prepared totally independently of the garage being built. These two activities<br />

have an independent or parallel relationship.<br />

Example project<br />

Table 16.2 identified the activities for the breakfast preparation project. The list shows that<br />

some of the activities must necessarily follow others. For example, ‘boil egg’ cannot be carried<br />

out until ‘fill pan with water’ and ‘bring water to boil’ have been completed. Further logical<br />

analysis of the activities in the list shows that there are two major ‘chains’, where activities<br />

must be carried out in a definite sequence:<br />

Slice bread – Toast bread – Butter toast<br />

Fill pan with water – Bring water to boil – Boil egg<br />

Both of these sequences must be completed before the activity ‘take loaded tray to bedroom’.<br />

The remaining activities (‘pour orange juice’ and ‘fetch tray, plates, cutlery’) can be done at<br />

any time provided that they are completed before ‘take loaded tray to bedroom’. An initial<br />

project plan might be as shown in Figure 16.9. Here, the activities have been represented<br />

as blocks of time in proportion to their estimated durations. From this, we can see that the<br />

‘project’ can be completed in nine minutes. Some of the activities have spare time (called<br />

float) indicated by the dotted line. The sequence ‘Fill pan – Boil water – Boil egg – Bedroom’<br />

has no float, and is called the critical path of the project. By implication, any activity which<br />

runs late in this sequence would cause the whole project to be delayed accordingly.<br />

Identify schedule constraints<br />

Once estimates have been made of the time and effort involved in each activity, and their<br />

dependencies identified, it is possible to compare project requirements with the available<br />

resources. The finite nature of critical resources – such as special skills – means that they<br />

should be taken into account in the planning process. This often has the effect of highlighting<br />

the need for more detailed replanning. There are essentially two fundamental approaches: 8<br />

●<br />

Resource-constrained. Only the available resource levels are used in resource scheduling,<br />

and are never exceeded. As a result, the project completion may slip. Resource-limited<br />

scheduling is used, for example, when a project company has its own highly specialized<br />

assembly and test facilities.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!