D. Compressed Air Piping: Unless otherwise directed by the authority having jurisdiction, flush<br />

piping with air until air flows clear for a minimum of 60 seconds per 100 linear feet of piping<br />

being flushed at 25 CFM per 1 inch diameter of pipe.<br />

E. All strainers <strong>and</strong> filters shall be cleaned <strong>and</strong> replaced prior to start-up.<br />

3.06 DISINFECTION OF DOMESTIC WATER PIPING SYSTEM<br />

A. Prior to starting work, verify system is complete, flushed <strong>and</strong> clean.<br />

B. Inject disinfectant, free chlorine in liquid, powder, tablet or gas form, throughout system to<br />

obtain 50 to 80 mg/L residual.<br />

C. Bleed water from outlets to ensure distribution <strong>and</strong> test for disinfectant residual at minimum 5<br />

remote outlets.<br />

D. Maintain disinfectant in system for 24 hours.<br />

E. Flush disinfectant from system until residual equal to that of incoming water or 1.0 mg/L.<br />

F. Take samples no sooner than 24 hours after flushing, from 5 remote outlets <strong>and</strong> from water<br />

entry, <strong>and</strong> analyze in accordance with AWWA C601.<br />

G. Disinfection <strong>and</strong> disinfection procedures shall be witnessed <strong>and</strong> approved by the Owners<br />

Representative.<br />

H. After disinfection is completed, submit "Disinfection Certificate of Approval" for domestic<br />

water piping systems to the Owners Representative stating that all test results are<br />

satisfactory. Certificate of Approval must be signed by Contractor, Testing Laboratory.<br />

Certificate shall show the date, time <strong>and</strong> residual of each of the following tests:<br />

1. Initial disinfection residual (50 PPM minimum) - 5 samples.<br />

2. Final disinfection residual (25 PPM minimum) - 5 samples.<br />

3. After flushing residual (5 PPM maximum) - 5 samples.<br />

4. Analyze in accordance AWWA C601 - 5 samples.<br />

3.07 CLOSING IN UNINSPECTED WORK<br />

Do not cover up or enclose work until it has been properly <strong>and</strong> completely inspected <strong>and</strong><br />

approved. Should any of the work be covered up or enclosed prior to all required inspections <strong>and</strong><br />

approvals, uncover the work as required. After it has been completely inspected <strong>and</strong> approved,<br />

make all repairs <strong>and</strong> replacements as necessary to the satisfaction of the Owner’s representative.<br />

Repairs <strong>and</strong> replacements shall be at no additional cost to the Owner.<br />

END OF SECTION<br />

Plumbing Systems 15400-18<br />