IEEE 1584<br />

NEC<br />

IEEE Guide for Performing Arc-Flash Hazard Calculations<br />

National Electrical Code<br />

1.03 SCHEDULE<br />

A. The report shall be provided to the ENGINEER NO LATER THAN 60 days before the equipment<br />

is shipped to the Work site. SHIPMENT AND DELIVERY OF EQUIPMENT WILL NOT BE<br />

ACCEPTED AT THE JOBSITE UNTIL THE STUDY HAS BEEN COMPLETED, SUBMITTED<br />

AND APPROVED BY THE ENGINEER.<br />

1.04 SUBMITTALS<br />

Submittals shall be in accordance with Section 01 33 00, SUBMITTALS <strong>and</strong> shall include:<br />

A. Short Circuit <strong>and</strong> Relay Coordination Study. Time current curves shall be on 11x17 log-log type<br />

paper. The CONTRACTOR can provide time current curves on 8 ½ x 11 log-log type paper as a<br />

supplement but not as a replacement.<br />

B. Arc Flash Hazard Analysis<br />

1. Provide a copy of project specific Arc Flash labels for each panelboard, disconnect, including<br />

all existing electrical equipment –starters, panelboards, etc.<br />

2. Provide a color copy of project specific Arc Flash labels for each panelboard, disconnect,<br />

motor control centers, transfer switches, including all existing electrical equipment –<br />

panelboards, starters, etc.<br />

3. Provide a 11x17 copy of the one-line diagram color-coded to show the incident ranges &<br />

clothing classifications at each bus. Provide a table indicating the color coding used for each<br />

incident range & clothing classification. The following is a recommended color coding for the<br />

following Hazard/Risk Category numbers:<br />

a. Green to indicate a Category 0<br />

b. Blue to indicate a Category 1<br />

c. Brown to indicate a Category 2<br />

d. Yellow to indicate a Category 3<br />

e. Orange to indicate a Category 4<br />

f. Red to indicate Above a Category 4<br />

C. Provide six (6) bound color copies of the completed short circuit <strong>and</strong> relay coordination study,<br />

the arc flash analysis shall be submitted to the ENGINEER for approval. Each hard copy of<br />

studies shall be bound in a 3-ring binder.<br />

D. Two Software copies of actual power systems computer program project data files burned in on<br />

a CD. The CONTRACTOR shall provide an electronic copy on a CD-ROM of all files used to<br />

develop the electrical system model in the power system analysis program <strong>and</strong> all files for the<br />

written study analysis <strong>and</strong> summary data tables. For instance if SKM software is used for the<br />

power system studies, then the SKM files shall be burned in on a CD-ROM <strong>and</strong> provided to the<br />

OWNER/ENGINEER. This shall include any library files used for circuit breakers, fuses, etc. for<br />

the power system analysis.<br />

Electrical Power System Studies 26 05 73.01-3<br />

DRP09328