5. A relay coordination study shall be performed to determine appropriate relay settings. The<br />

study shall include all electrical equipment provided under this contract <strong>and</strong> any up-stream<br />

equipment that has an impact on the coordination study. The study shall show transformer<br />

damage curves, generator damage curves, cable short circuit withst<strong>and</strong> curves <strong>and</strong> motor<br />

curves. <strong>Inc</strong>lude all medium <strong>and</strong> low voltage switchgear, distribution switchboards, motor<br />

control centers, starters, <strong>and</strong> panelboards main circuit breakers. Complete the short circuit<br />

study down to the main breaker or main lugs on all panelboards. Panelboard branch circuit<br />

devices need not be considered. The phase over current <strong>and</strong> ground-fault protection shall be<br />

included as well as settings for all other adjustable protective devices. All motor monitoring<br />

relays <strong>and</strong> protective or monitoring devices that are a part of a supplier’s equipment (such as<br />

soft starters, switchgear) shall be in included. <strong>Inc</strong>lude the last protective device in the Electric<br />

Utility’s system feeding each facility being considered.<br />

6. Provide Time-Current Curves on 11X17 log-log paper. Do not put more than one branch of<br />

protective devices on any one coordination curve. <strong>Inc</strong>lude a one-line diagram <strong>and</strong> the names<br />

of each protective device in the branch. Use the names designated in the Contract<br />

Documents. <strong>Inc</strong>lude motor <strong>and</strong> transformer damage curves, <strong>and</strong> cable short circuit<br />

withst<strong>and</strong> curves. Coordination study time-current curves (11x17 log-log type) including the<br />

instrument transformer ratios, model numbers of the protective relays, <strong>and</strong> the relay settings<br />

associated with each breaker. Organize the curves as specified here in. Ground fault time<br />

current curves shall be on a separate sheet.<br />

7. An equipment evaluation study shall be performed to determine the adequacy of the fault<br />

bracing of all bus from the panelboard level up to the main Panelboard or protective device.<br />

<strong>Inc</strong>lude circuit breakers, controllers, surge arresters, busway, switches, <strong>and</strong> fuses by<br />

tabulating <strong>and</strong> comparing the short circuit ratings of these devices with the available fault<br />

currents.<br />

8. Provide arc flash hazard analysis in accordance with the applicable NFPA, ANSI, <strong>and</strong> IEEE<br />

st<strong>and</strong>ards.<br />

9. The studies shall be performed, sealed <strong>and</strong> signed by a Registered Professional Engineer<br />

licensed in the state of Texas.<br />

10. Any problem areas or inadequacies in the equipment shall be promptly brought to the<br />

ENGINEER's attention.<br />

11. Use industry st<strong>and</strong>ard short circuit software, SKM CAPTOR <strong>and</strong> DAPPER or an equal<br />

approved by the ENGINEER.<br />

12. The report shall include a comparison of short circuit duties of each bus to the interrupting<br />

capacity of the equipment that is protecting that bus.<br />

13. The report shall include all data that was used as input to the report. This data shall include<br />

cable impedance, conduit type, source impedance, equipment ratings, motor X/R <strong>and</strong><br />

subtransient reactance data, etc.<br />

14. The CONTRACTOR shall coordinate with the OWNER for electrical data required for the<br />

studies.<br />

1.02 REFERENCES<br />

A. This Section contains references to the following documents. They are a part of this Section as<br />

specified <strong>and</strong> modified. In case of conflict between the requirements of this Section <strong>and</strong> those of<br />

the listed documents, the requirements of this Section shall prevail.<br />

Reference<br />

IEEE 141<br />

Title<br />

Recommended Practice for Electric Power Distribution for Industrial<br />

Plants<br />

IEEE 242<br />

NFPA 70E<br />

Recommended Practice for Protection <strong>and</strong> Coordination of Industrial <strong>and</strong><br />

Commercial Power Systems<br />

H<strong>and</strong>book for Electrical Safety in the Workplace<br />

Electrical Power System Studies 26 05 73.01-2<br />

DRP09328