28.04.2015 Views

final bid specs 09328.pdf - Freese and Nichols, Inc.

final bid specs 09328.pdf - Freese and Nichols, Inc.

final bid specs 09328.pdf - Freese and Nichols, Inc.

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

26 05 73.01 ELECTRICAL POWER SYSTEM STUDIES<br />

1.00 GENERAL<br />

1.01 DESCRIPTION<br />

General: This section specifies that the CONTRACTOR prepare a short circuit <strong>and</strong> relay coordination<br />

study <strong>and</strong> an arc flash hazard analysis for the electrical power system as shown on the plans.<br />

Short Circuit <strong>and</strong> Relay Coordination Study, Arc Flash Analysis<br />

The studies shall provide an evaluation of the electrical power system <strong>and</strong> the model numbers <strong>and</strong><br />

settings of the protective relays or devices <strong>and</strong> metering or motor monitoring devices for setting by the<br />

CONTRACTOR. The Studies shall include settings for all motor protective relays <strong>and</strong> electric system<br />

monitoring.<br />

A. Scope:<br />

1. The CONTRACTOR is responsible for providing all pertinent information necessary for the<br />

successful completion of the Short Circuit <strong>and</strong> Relay Coordination Study <strong>and</strong> Arc Flash<br />

Analysis. All cable <strong>and</strong> raceway data, data for existing motors, data from all new Switchgear,<br />

motor control centers, transformers, panelboards, <strong>and</strong> separately mounted fuses, starters or<br />

circuit breakers shall be obtained by the CONTRACTOR. Obtain all existing or new<br />

protective device information to include all present settings. The CONTRACTOR shall obtain<br />

any needed data or information from Contract Documents, various suppliers, the Electric<br />

Utility <strong>and</strong> from conducting his own field investigations. The data obtained shall be organized<br />

<strong>and</strong> submitted to the ENGINEER to show that all the necessary data gathering work has<br />

been done.<br />

2. Calculations shall utilize actual X/R <strong>and</strong> three phase short circuit values obtained by the<br />

CONTRACTOR from the Electric Utility. The use of infinite bus fault current calculation is not<br />

acceptable.<br />

3. The studies shall model the electrical distribution system feeding the building all the way back<br />

to the Utility owned transformer. Contractor shall include all loads normally fed from the utility<br />

owned transformer.<br />

4. Provide a complete short circuit study. <strong>Inc</strong>lude three phase <strong>and</strong> phase-to-ground<br />

calculations. Provide an equipment interrupting or withst<strong>and</strong> evaluation based on the actual<br />

equipment <strong>and</strong> model numbers provided on this project. Generic devices are not acceptable.<br />

Normal system operating method, alternate operation, <strong>and</strong> operations that could result in<br />

maximum fault conditions shall be thoroughly addressed in the study. The study shall assume<br />

all motors operating at rated voltage with the exception that motors identified as "st<strong>and</strong>by"<br />

shall not be included. Electrical equipment bus impedance shall be assumed zero. Short<br />

circuit momentary duties <strong>and</strong> interrupting duties shall be calculated on the basis of maximum<br />

available fault current at the electrical equipment busses. The Study shall be performed<br />

using actual available short circuit currents available <strong>and</strong> system impedances as obtained<br />

from the Electric Utility. An assumption of infinite bus for the purposes of the Study is not<br />

acceptable. Study shall use actual motor X/R <strong>and</strong> subtransient reactance data obtained from<br />

equipment suppliers.<br />

Electrical Power System Studies 26 05 73.01-1<br />

DRP09328

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!