The <str<strong>on</strong>g>12th</str<strong>on</strong>g> <str<strong>on</strong>g>Internati<strong>on</strong>al</str<strong>on</strong>g> <str<strong>on</strong>g>Symposium</str<strong>on</strong>g> <strong>on</strong> <strong>District</strong> <strong>Heating</strong> <strong>and</strong> <strong>Cooling</strong>,September 5 th to September 7 th , 2010, Tallinn, Est<strong>on</strong>iarequirements, <strong>and</strong> the different flow requirements, theexergy used by each system was unique.Capital <strong>and</strong> Exergy Cost AssessmentsAll cost numbers reported in this paper are in 2009Canadian Dollars. An in-house costing tool was used toestimate cost for the district heating energy centre,c<strong>on</strong>taining the pumps <strong>and</strong> boilers, <strong>and</strong> the burieddistributi<strong>on</strong> piping. For the two heating systemsc<strong>on</strong>sidered, the costs were assigned as shown inTable I. For water-to-air fan coils (cross-flow heatexchangers) an installed cost of $250/m2 wasc<strong>on</strong>sidered representative, <strong>and</strong> for radiators $200/m2was selected as a typical value.Table I. – Cost for heating technologiesCross-flow heatexchangerRadiative system$250/m 2 of heat transfer surface$200/m 2 of exposed panelFuture cash flows were discounted at a rate of 8% <strong>and</strong>system lifetime was set at 40 years. Annual operating<strong>and</strong> maintenance (O&M) cost other than cost for heat<strong>and</strong> electricity were set at a fixed fracti<strong>on</strong> of 1% of totalinvestment cost.To compare traditi<strong>on</strong>al optimizati<strong>on</strong> with exergoec<strong>on</strong>omicoptimizati<strong>on</strong> three types of analyses wereperformed. The ‗classical analysis‘ applies thetraditi<strong>on</strong>al optimizati<strong>on</strong> where heat is valued based <strong>on</strong>energy c<strong>on</strong>tent, at a rate of $5/GJ, which is c<strong>on</strong>sideredrepresentative for heat from natural gas combusti<strong>on</strong>.Electricity cost has been set at $17/GJ (just over$60/MWh).In the exergoec<strong>on</strong>omic analysis heat <strong>and</strong> electricity arepriced based <strong>on</strong> the exergy c<strong>on</strong>tent. The exergy chargewas determined at $30/GJ for thermal energy, based<strong>on</strong> the above menti<strong>on</strong>ed $5/GJ for heat, assuming a 1to 6 ratio of exergy to energy c<strong>on</strong>tent (applies to atemperature around 80 °C). The electrical energy toexergy ratio was taken as <strong>on</strong>e, resulting in an exergycharge of $17/GJ for electricity. At first glace it mayseem err<strong>on</strong>eous to charge more for exergy from thethermal source than that for the electricity for the pump,but it must be remembered that the (thermal) exergy isa fracti<strong>on</strong> of the thermal energy.The third type of analysis is a classical analysiscorrected for the difference in value of low- <strong>and</strong> hightemperatureheat, by assuming energy under 60°C isavailable free of charge (as waste heat from a nearbyprocess). For energy over 60 °C the charge is still$5/GJ.To assess the influence of carb<strong>on</strong> taxes, two sets ofresults are presented. One assumes no carb<strong>on</strong> taxesare in place <strong>and</strong> the other assumes a carb<strong>on</strong> tax of $3049per t<strong>on</strong> CO2eq. Carb<strong>on</strong> intensity factors of 0.050 t<strong>on</strong>CO2eq/GJ were used for natural gas <strong>and</strong> 0.054 t<strong>on</strong>CO2eq/GJ for electricity (taken from RETScreen [6] asrepresentative for Canada). This results in a $6.5/GJenergy charge for heat, a $38.9/GJ exergy charge forheat <strong>and</strong> an $18.6/GJ energy (or exergy) charge forelectricity.Thermoec<strong>on</strong>omic FactorThe exergoec<strong>on</strong>omic or thermoec<strong>on</strong>omic factor ―f‖compares two sources c<strong>on</strong>tributing to cost, investmentrelatedcost <strong>and</strong> exergy destructi<strong>on</strong> cost. It is definedhere as the ratio of Capital Cost Rate (CCR, whichincludes O&M cost, but excludes heat <strong>and</strong> electricitycost) <strong>and</strong> the sum of Exergy Destructi<strong>on</strong> Cost Rate(EDCR) <strong>and</strong> CCR. The CCR equals the cost per unittime for the installati<strong>on</strong>, depreciati<strong>on</strong>, maintenance, etc,while EDCR is the cost of exergy.fCCREDCR CCR (4)Since CCR <strong>and</strong> EDCR have the dimensi<strong>on</strong>s of $/time,―f‖ is dimensi<strong>on</strong>less.A high value for ―f‖ indicates that the capital <strong>and</strong>maintenance costs are dominant. Also, a high f – valueindicates good use of the exergy in the fuel. On theother h<strong>and</strong>, a low value for ―f‖ indicates an inefficientuse of fuel resources. For each heating systemvariati<strong>on</strong>, the average annual thermoec<strong>on</strong>omic factorwas calculated.MODELLING RESULTSBase case designTable II shows the main informati<strong>on</strong> for the base casedesigns for both the radiator <strong>and</strong> cross-flow heatexchanger systems. As expected, the distributi<strong>on</strong> pipediameters, required pump capacity, annual space heatc<strong>on</strong>sumpti<strong>on</strong> <strong>and</strong> annual heat cost are the same forboth systems.As the water return temperatures throughout the yearare generally lower for the radiator system, the requiredwater flows <strong>and</strong> c<strong>on</strong>sequently the annual electricityc<strong>on</strong>sumpti<strong>on</strong> are lower for the radiator system. As bothsystems have a design supply temperature of 90 °C(<strong>and</strong> thus also the same off-design supplytemperatures throughout the year), the annual exergyc<strong>on</strong>sumpti<strong>on</strong> is the same for both. The lower returntemperatures for the radiator system also show in thehigher fracti<strong>on</strong> of energy provided under 60 °C. Interms of cost, the radiators are clearly more expensiveresulting in higher annual investment <strong>and</strong> O&M cost,which is not offset by the somewhat lower electricitycost. Overall the more capital intensive radiator systemhas a higher f-factor than the cross-flow heat
The <str<strong>on</strong>g>12th</str<strong>on</strong>g> <str<strong>on</strong>g>Internati<strong>on</strong>al</str<strong>on</strong>g> <str<strong>on</strong>g>Symposium</str<strong>on</strong>g> <strong>on</strong> <strong>District</strong> <strong>Heating</strong> <strong>and</strong> <strong>Cooling</strong>,September 5 th to September 7 th , 2010, Tallinn, Est<strong>on</strong>iaexchanger system. In a comparis<strong>on</strong> between the twosystems, the cross-flow heat exchanger system worksout cheaper using all three types of analysis due to thelarge difference in investment cost.Table II. – Main informati<strong>on</strong> base case designs withoutCO 2 tax.RadiatorCross-flowheatexchangerSurface area (m 2 ) 42,271 17,152Distributi<strong>on</strong> pipediameters (mm) DN80/DN65 DN80/DN65Required pump capacity(kW) 32.2 32.2Annual electricityc<strong>on</strong>sumpti<strong>on</strong> (GJ) 115.2 147.6Annual exergyc<strong>on</strong>sumpti<strong>on</strong> (GJ) 16,810 16,810Annual space heatc<strong>on</strong>sumpti<strong>on</strong> (GJ) 100,000 100,000Fracti<strong>on</strong> of energy < 60 °C 68.4% 64.4%Installed cost heaters $8,454,298 $4,288,066Investment cost districtheating system $11,556,386 $11,556,386Annual O&M cost $200,107 $158,445Annual charge investment<strong>and</strong> O&M cost $1,878,206 $1,487,163Annual heat (energy) cost $500,000 $500,000Annual heat (exergy) cost $504,193 $504,193Annual electricity cost $1,958 $2,509Total annual cost classicalanalysis $2,380,164 $1,989,672Total annual costexergoec<strong>on</strong>omic analysis $2,384,357 $1,993,865Total annual cost heatunder 60 °C free analysis $2,038,164 $1,667,672f-factor 0.814 0.782Alternative designs – radiator systemFor both the radiator <strong>and</strong> the cross-flow heatexchanger system alternative designs with increased<strong>and</strong> decreased surface areas were costed. The districtheat supply temperatures were modified accordingly,<strong>and</strong> as noted before, the required water flows <strong>and</strong> thusdistributi<strong>on</strong> pipe diameters <strong>and</strong> pumping powerrequirements were modified too. The effects of thesevariati<strong>on</strong>s <strong>on</strong> cost were taken into account.The results of all the modelling runs are shown in thefigures below in the form of the relati<strong>on</strong>ship betweenthe annual cost (the sum of capital investment, O&Mcost <strong>and</strong> energy or exergy costs) <strong>and</strong> the f-factor. Anincreasing f-factor means increasing surface areas(<strong>and</strong> thus increasing capital <strong>and</strong> operating <strong>and</strong>maintenance cost) <strong>and</strong> decreasing heat supplytemperatures (<strong>and</strong> thus decreasing exergy cost).Figure 2 shows results for the radiator based heatingsystem with no carb<strong>on</strong> taxes in place. The slight jumpin annual cost around an f-factor of 0.81-0.82 is causedby an increase in district heating piping diameter fromDN65 to DN80 for the 80-house streets <strong>and</strong> from DN50to DN65 for the 40-house. All lower f-factors shownhave piping diameters of DN65 <strong>and</strong> DN50 <strong>and</strong> allhigher f-factors shown have DN80 <strong>and</strong> DN65respectively.Annual cost ($)$2,900,000$2,700,000$2,500,000$2,300,000$2,100,000$1,900,000$1,700,000$1,500,0000.68 0.70 0.72 0.74 0.76 0.78 0.80 0.82 0.84 0.86 0.88f-factor (-)Classical analysis Exergo-ec<strong>on</strong>omic analysis Heat under 60C free analysisFig. 2. Relati<strong>on</strong> between f-factor <strong>and</strong> annual cost radiatorsystem, no carb<strong>on</strong> tax.The classical analysis shows a c<strong>on</strong>tinuous increase inannual cost with increasing f-factor. 1 This makes sensebecause cost is not based <strong>on</strong> exergy but <strong>on</strong> energy.Therefore, an increasing surface area meansincreasing capital cost, but c<strong>on</strong>stant energy cost, so thelower exergy requirement does not offset the increasein capital cost. The classical analysis would tell us tooptimize the system with minimum capital expenses. Inreality there would be a limit as ever increasingtemperatures will mean that we are dealing with moreexpensive materials <strong>and</strong> at a certain stage steaminstead of hot water, requiring a more expensive districtheating system. Also, heat losses to the envir<strong>on</strong>ment501 Although exergy is not explicitly costed in the classical analysis,we can still calculate an f-factor.
- Page 1: 12th Inter
- Page 5 and 6: The 12th I
- Page 7 and 8: The 12th I
- Page 10 and 11: The 12th I
- Page 12 and 13: The 12th I
- Page 14 and 15: For the case of parallel buried pip
- Page 16 and 17: The 12th I
- Page 18 and 19: The 12th I
- Page 20 and 21: The 12th I
- Page 22 and 23: The 12th I
- Page 24 and 25: The 12th I
- Page 26 and 27: The 12th I
- Page 28 and 29: The 12th I
- Page 30 and 31: The 12th I
- Page 32 and 33: The 12th I
- Page 34 and 35: The 12th I
- Page 36 and 37: The 12th I
- Page 38 and 39: The 12th I
- Page 40 and 41: The 12th I
- Page 42 and 43: The 12th I
- Page 44 and 45: The 12th I
- Page 46 and 47: The 12th I
- Page 48 and 49: The 12th I
- Page 52 and 53: The 12th I
- Page 54 and 55: The 12th I
- Page 56 and 57: The 12th I
- Page 58 and 59: The 12th I
- Page 60 and 61: The 12th I
- Page 62 and 63: The 12th I
- Page 64 and 65: The 12th I
- Page 66 and 67: The 12th I
- Page 68 and 69: The 12th I
- Page 70 and 71: The 12th I
- Page 72 and 73: The 12th I
- Page 74 and 75: The 12th I
- Page 76 and 77: The 12th I
- Page 78 and 79: The 12th I
- Page 80 and 81: The 12th I
- Page 82 and 83: The 12th I
- Page 84 and 85: The 12th I
- Page 86 and 87: The 12th I
- Page 88 and 89: The 12th I
- Page 90 and 91: The 12th I
- Page 92 and 93: The 12th I
- Page 94 and 95: The 12th I
- Page 96 and 97: The 12th I
- Page 98 and 99: the street the more shallow the sha
- Page 100 and 101:
The 12th I
- Page 102 and 103:
The 12th I
- Page 104 and 105:
The 12th I
- Page 106 and 107:
The 12th I
- Page 108 and 109:
The 12th I
- Page 110 and 111:
P-1P-4P-9P-7E-5P-14P-8The 1
- Page 112 and 113:
The 12th I
- Page 114 and 115:
The 12th I
- Page 116 and 117:
The 12th I
- Page 118 and 119:
The 12th I
- Page 120 and 121:
The 12th I
- Page 122 and 123:
The 12th I
- Page 124 and 125:
The 12th I
- Page 126 and 127:
The 12th I
- Page 128 and 129:
The 12th I
- Page 130 and 131:
The 12th I
- Page 132 and 133:
The 12th I
- Page 134 and 135:
The 12th I
- Page 136 and 137:
The 12th I
- Page 138 and 139:
to heating costs of 14,5 ct/kWh. Th
- Page 140 and 141:
The 12th I
- Page 142 and 143:
The 12th I
- Page 144 and 145:
The 12th I
- Page 146 and 147:
The 12th I
- Page 148 and 149:
academic access is facilitated as t
- Page 150 and 151:
The 12th I
- Page 152 and 153:
The 12th I
- Page 154 and 155:
The 12th I
- Page 156 and 157:
The 12th I
- Page 158 and 159:
The 12th I
- Page 160 and 161:
The 12th I
- Page 162 and 163:
1. CHP system operation in A2. Ther
- Page 164 and 165:
The 12th I
- Page 166 and 167:
is covered by operating HOB. In oth
- Page 168 and 169:
The 12th I
- Page 170 and 171:
The 12th I
- Page 172 and 173:
The 12th I
- Page 174 and 175:
The 12th I
- Page 176 and 177:
The 12th I
- Page 178 and 179:
The 12th I
- Page 180 and 181:
The 12th I
- Page 182 and 183:
The 12th I
- Page 184 and 185:
The 12th I
- Page 186 and 187:
The 12th I
- Page 188 and 189:
The 12th I
- Page 190 and 191:
The 12th I
- Page 192 and 193:
The 12th I
- Page 194 and 195:
The 12th I
- Page 196 and 197:
produce heat and electricity. Fluct
- Page 198 and 199:
The 12th I
- Page 200 and 201:
The 12th I
- Page 202 and 203:
The 12th I
- Page 204 and 205:
The 12th I
- Page 206 and 207:
The 12th I
- Page 208 and 209:
The 12th I
- Page 210 and 211:
To assure that the temperatures mea
- Page 212 and 213:
The 12th I
- Page 214 and 215:
The 12th I
- Page 216 and 217:
The 12th I
- Page 218 and 219:
The 12th I
- Page 220 and 221:
production and provide for marginal
- Page 222 and 223:
The 12th I
- Page 224 and 225:
The 12th I
- Page 226 and 227:
The 12th I
- Page 228 and 229:
The 12th I
- Page 230 and 231:
The 12th I
- Page 232 and 233:
The 12th I
- Page 234 and 235:
The 12th I
- Page 236 and 237:
The 12th I
- Page 238 and 239:
The 12th I
- Page 240 and 241:
The 12th I
- Page 242 and 243:
In addition, it can also be observe
- Page 244 and 245:
The 12th I
- Page 246 and 247:
owner is normally only interested i
- Page 248 and 249:
The 12th I
- Page 250 and 251:
The 12th I
- Page 252 and 253:
The 12th I
- Page 254 and 255:
The 12th I
- Page 256 and 257:
The 12th I
- Page 258 and 259:
The 12th I
- Page 260 and 261:
The 12th I
- Page 262 and 263:
The 12th I
- Page 264 and 265:
The 12th I
- Page 266 and 267:
The 12th I
- Page 268 and 269:
The 12th I
- Page 270 and 271:
The 12th I
- Page 272 and 273:
The 12th I
- Page 274 and 275:
The 12th I
- Page 276 and 277:
The 12th I
- Page 278 and 279:
The 12th I
- Page 280 and 281:
The 12th I
- Page 282 and 283:
The 12th I
- Page 284 and 285:
The 12th I
- Page 286 and 287:
The 12th I
- Page 288 and 289:
The 12th I
- Page 290 and 291:
Stockholm district heating system a
- Page 292 and 293:
The 12th I
- Page 294 and 295:
The 12th I
- Page 296 and 297:
The 12th I
- Page 298 and 299:
The 12th I
- Page 300 and 301:
The 12th I
- Page 302 and 303:
The 12th I
- Page 304 and 305:
The 12th I
- Page 306 and 307:
The 12th I
- Page 308 and 309:
The 12th I
- Page 310 and 311:
The 12th I
- Page 312 and 313:
The 12th I
- Page 314 and 315:
The values presented do of course l
- Page 316 and 317:
The 12th I
- Page 318 and 319:
The 12th I
- Page 320 and 321:
The 12th I
- Page 322 and 323:
The 12th I
- Page 324 and 325:
The 12th I
- Page 326:
The 12th I