04.08.2013 Views

FMS - GAIL

FMS - GAIL

FMS - GAIL

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

27.3<br />

Bonus For Early<br />

Completion (*)<br />

28 Rights of the employer to<br />

forfeit contract<br />

performance security:<br />

29 Failure by the contractor<br />

to comply with the<br />

provisions of the<br />

contract:<br />

27.2 All sums payable under this clause is the reduction in price due to<br />

delay in completion period at the above agreed rate.<br />

27.3 BONUS FOR EARLY COMPLETION<br />

If the Contractor achieves completion of Works in all respect prior to<br />

the time schedule stipulated in the SCC, the Employer shall pay to<br />

the Contractor the relevant sum, if mentioned specifically in SCC, as<br />

bonus for early completion. The bonus for early completion, if<br />

provided specifically in SCC, shall be payable to the maximum<br />

ceiling of 2 ½ % of the total contract price.<br />

(*) Partial earlier completion may not always produce net benefits to the<br />

Employer, for example where utilization of the completed Works<br />

requires (a) the fulfillment of all parts of the Contract (e.g. the training<br />

of personnel); or (b) the completion of all Sections (e.g. in pipeline<br />

laying, where early completion of the laying of pipeline would not be<br />

useful if the compressor is still under installation); or (c) certain<br />

seasonal effects to take place (e.g. onset of the rainy season, for<br />

impounding a reservoir); or (d) other circumstances. Also a more<br />

rapid drawdown of budgeted funds may be required. All such factors<br />

should be considered prior to the inclusion of a bonus clause in the<br />

Contract.<br />

28.1 Whenever any claim against the CONTRACTOR for the payment of<br />

a sum of money arises out or under the CONTRACT, the<br />

EMPLOYER shall be entitled to recover such sum by appropriating<br />

in part or whole the Contract Performance Security of the<br />

CONTRACTOR. In the event of the security being insufficient or if<br />

no security has been taken from the CONTRACTOR, then the<br />

balance or the total sum recoverable, as the case may be shall be<br />

deducted from any sum then due or which at any time thereafter may<br />

become due to the CONTRACTOR. The CONTRACTOR shall pay<br />

to the EMPLOYER on demand any balance remaining due.<br />

29.1 If the CONTRACTOR refuses or fails to execute the WORK or any<br />

separate part thereof with such diligence as will ensure its<br />

completion within the time specified in the CONTRACT or extension<br />

thereof or fails to perform any of his obligation under the<br />

CONTRACT or in any manner commits a breach of any of the<br />

provisions of the CONTRACT it shall be open to the EMPLOYER at<br />

its option by written notice to the CONTRACTOR:<br />

a) TO DETERMINE THE CONTRACT in which event<br />

the CONTRACT shall stand terminated and shall cease to<br />

be in force and effect on and from the date appointed by the<br />

EMPLOYER on that behalf, whereupon the CONTRACTOR<br />

shall stop forthwith any of the CONTRACTOR's work then in<br />

progress, except such WORK as the EMPLOYER may, in<br />

writing, require to be done to safeguard any property or<br />

WORK, or installations from damage, and the EMPLOYER,<br />

for its part, may take over the work remaining unfinished by<br />

the CONTRACTOR and complete the same through a fresh<br />

contractor or by other means, at the risk and cost of the<br />

CONTRACTOR, and any of his sureties if any, shall be<br />

liable to the EMPLOYER for any excess cost occasioned by<br />

such work having to be so taken over and completed by the<br />

EMPLOYER over and above the cost at the rates specified<br />

in the schedule of quantities and rate/prices.<br />

b) WITHOUT DETERMINING THE CONTRACT to<br />

66

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!