CONTRACTOR.<br />

c) If the rates for the altered, additional or<br />

substituted WORK cannot be determined in the<br />

manner specified in sub-clause(s) and (b) above,<br />

then the CONTRACTOR shall, within 7 days of<br />

the date of receipt of order to carry out the<br />

WORK, inform the ENGINEER-IN-CHARGE of<br />

the rates which it is his intention to charge for<br />

such class of WORK, supported by analysis of<br />

the rate or rates claimed, and the<br />

ENGINEER-IN-CHARGE shall determine the<br />

rate or rates on the basis of the prevailing market<br />

rates, labour cost at schedule of labour rates<br />

plus 10% to cover contractor's supervision,<br />

overheads and profit and pay the<br />

CONTRACTOR accordingly. The opinion of the<br />

ENGINEER- IN-CHARGE as to current market<br />

rates of materials and the quantum of labour<br />

involved per unit of measurement will be final<br />

and binding on the CONTRACTOR.<br />

d) Where the item of work will be executed through<br />

nominated specialist agency as approved by the<br />

ENGINEER-IN-CHARGE, then the actual<br />

amount paid to such nominated agency<br />

supported by documentary evidence and as<br />

certified by ENGINEER-IN-CHARGE shall be<br />

considered plus 10% (ten percent) to cover all<br />

contingencies, overhead, profits to arrive at the<br />

rates.<br />

e) Provisions contained in the Sub-clause (a) & (d)<br />

above shall, however, not apply for the<br />

following:-<br />

Where the value of additions of new items<br />

together with the value of alterations,<br />

additions/deletions or substitutions does not<br />

exceed by or is not less than plus/minus (+_)25%<br />

of the VALUE OF CONTRACT. The item rates in<br />

the Schedule of Rates shall hold good for all<br />

such variations between the above mentioned<br />

limits, irrespective of any increase/decrease of<br />

quantities in the individual items of Schedule of<br />

Rates.<br />

Where the value of addition of new items<br />

together with the value of alterations,<br />

additions/deletions or substitutions reduces more<br />

than 25% of the contract value but is within the<br />

following limits the tenderer shall be paid<br />

compensation for decrease in the value of work,<br />

as follows:<br />

S.No. Range of Variation Percentage compensation for<br />

decrease in the value of work<br />

in the respective range.<br />

a) Beyond (+) 25% upto & No increase and/or decrease<br />

inclusive of (+) 50% shall be applicable for the<br />

Schedule of Rates (The rates<br />

quoted for this increase shall<br />

80