88 Procedure for measurement<br />

and billing of work in<br />

progress:<br />

or State Government or local Body or Municipal Taxes or<br />

duties, taxes or charges (from or of any other body),<br />

whatsoever, will be granted or obtained, all of which<br />

expenses shall be deemed to be included in and covered<br />

by the Schedule or Rates. The CONTRACTOR shall also<br />

obtain and pay for all permits or other privileges necessary<br />

to complete the WORK.<br />

vi) SCHEDULE OF RATES TO COVER RISKS OF DELAY:<br />

The Schedule of Rates shall be deemed to include and<br />

cover the risk of all possibilities of delay and interference<br />

with the CONTRACTOR's conduct of WORK which occur<br />

from any causes including orders of the EMPLOYER in the<br />

exercise of his power and on account of extension of time<br />

granted due to various reasons and for all other possible or<br />

probable causes of delay.<br />

vii) SCHEDULE OF RATES CANNOT BE ALTERED:<br />

For WORK under unit rate basis, no alteration will be<br />

allowed in the Schedule of Rates by reason of works or any<br />

part of them being modified, altered, extended, diminished<br />

or committed. The Schedule of Rates are fully inclusive of<br />

rates which have been fixed by the CONTRACTOR and<br />

agreed to by the EMPLOYER and cannot be altered.<br />

For lumpsum CONTRACTS, the payment will be made<br />

according to the WORK actually carried out, for which<br />

purpose an item wise, or work wise Schedule of Rates shall<br />

be furnished, suitable for evaluating the value of WORK<br />

done and preparing running account bill.<br />

Payment for any additional work which is not covered in the<br />

Schedule of Rates, shall only be released on issuance of<br />

change order.<br />

88.1 BILLING PROCEDURE:<br />

Following procedures shall be adopted for billing of works executed<br />

by the CONTRACTOR.<br />

88.1.1 All measurements shall be recorded in sextuplicate on standard<br />

measurement sheets supplied by EMPLOYER and submitted to<br />

EMPLOYER/CONSULTANT for scrutiny and passing.<br />

88.1.2 EMPLOYER/CONSULTANT shall scrutinise and check the<br />

measurements recorded on the sheets and shall certify correctness<br />

of the same on the measurement sheets.<br />

88.1.3 ENGINEER-IN-CHARGE shall pass the bills after carrying out the<br />

comprehensive checks in accordance with the terms and conditions<br />

of the CONTRACTS, within 7 days of submission of the bills,<br />

complete in all respects and send the same to the Employer to<br />

effect payment to the CONTRACTOR.<br />

88.1.4 <strong>GAIL</strong> shall make all endeavour to make payments of undisputed<br />

amount of the bills submitted based on the joint measurements<br />

within 15 (Fifteen) days from the date of certification by the<br />

Engineer-in-Charge.<br />

88.1.5 Measurements shall be recorded as per the methods of<br />

measurement spelt out in EMPLOYER/CONSULTANT<br />