168<br />

Results of atmospheric test: NB. Attach certifi cate of test results of this PTW<br />

form<br />

Test no..........................Date......./......./....... Result..............% oxygen<br />

The following precautions will be taken during the works:<br />

1. A trained person not directly involved with the work will provide a continuous fi re watch during the<br />

period of hot work<br />

2. At least two suitable extinguishers are immediately available. Personnel undertaking the work and<br />

providing the fi re watch are trained in their use<br />

3. Emergency arrangements <strong>to</strong> s<strong>to</strong>p work, make safe area and evacuate have been established (if<br />

alarm not set off by hot work processes)<br />

Part C Acceptance<br />

I have read and unders<strong>to</strong>od this permit and will ensure that all the precautions detailed in<br />

Part B above have been, or will be taken.<br />

Signed...............................................Position......................................................Date...../...../.....at.....hrs<br />

Part D Completion<br />

I declare that the permitted hot work has been completed...........................on...../...../....at.....hrs<br />

Signed................................................Position...................................................... Date...../...../.....at.....hrs<br />

Part E Request for an extension<br />

The work has not been completed and an extension is requested<br />

Signed..........................................Position.................................................Date...../...../.....at.....hrs<br />

Part F Extension<br />

I have re-examined the area and confi rm that the permit may be extended <strong>to</strong>..../...../...../at.....hrs<br />

Signed.................................................Position......................................................Date...../...../.....<br />

Part G Cancellation of Permit<br />

I hereby declare that this permit <strong>to</strong> work is cancelled and that all specifi ed precautionary<br />

measures have been withdrawn or reinstated.<br />

Signed............................................Position...............................................Date...../...../.....at.....hrs<br />

Part H <strong>Fire</strong> Watch<br />

The work area and all adjacent areas <strong>to</strong> which sparks and heat may have spread (such as fl oors<br />

below and above, and areas on other side of walls) have been inspected and found <strong>to</strong> be free<br />

of fi re following completion of work (minimum of 1 hour following cessation of works)<br />

Signed.................................................Position..........................................Date...../...../.....at.....hrs<br />

Part I Hand back of area<br />

I hereby confi rm that the works have been completed satisfac<strong>to</strong>rily, the area is safe and the<br />

detection/sprinkler system are fully functional<br />

Signed.................................................Position..........................................Date...../...../.....at.....hrs<br />

NB a copy of the Method Statement and risk assessment for the works should be attached <strong>to</strong> this form