PHILIP W. NAKONESHNY<br />

DIRECTOR, RATES AND FINANCE<br />

Philip.Nakoneshny@bcuc.com<br />

web site: http://www.bcuc.com<br />

Erica M. Hamilton<br />

Commission Secretary<br />

British Columbia Utilities Commission<br />

Sixth floor, 900 Howe Street, Box 250<br />

Vancouver, BC V6Z 2N3<br />

Dear Ms. Hamilton:<br />

November 13, 2009<br />

Re: Terasen Gas Inc.<br />

<strong>2010</strong> and <strong>2011</strong> Revenue Requirements Application<br />

Negotiated Settlement Agreement<br />

Letter of Comment<br />

SIXTH FLOOR, 900 HOWE STREET, BOX 250<br />

VANCOUVER, B.C. CANADA V6Z 2N3<br />

TELEPHONE: (604) 660‐4700<br />

BC TOLL FREE: 1‐800‐663‐1385<br />

FACSIMILE: (604) 660‐1102<br />

Commission staff participated in the settlement discussions that led to a Negotiated Settlement Agreement<br />

(“Settlement Agreement”) being reached between Terasen Gas Inc. (“Terasen Gas”) and the registered<br />

Intervenors (collectively, the “Parties”) in accordance with the Negotiated Settlement Process‐Policy, Procedures<br />

and Guidelines, January 2001 (“NSP Guidelines”). Commission staff has informed the Parties that the<br />

agreements reached on certain issues were not supported by Commission staff and that Commission staff<br />

intended to submit a Letter of Comment in respect of those issues. The Parties agreed to Commission staff<br />

adopting that course.<br />

There are three items in the Settlement Agreement that Commission staff do not support:<br />

1. Item 10‐Inclusion of SCP Capacity in MCRA<br />

APPENDIX A<br />

to Order G-141-09<br />

Page 105 of 110<br />

Commission Order G‐98‐05 states that:<br />

“The Commission approves the debiting of the annual charge of $3.6 million (based on the monthly<br />

instalments) against the Midstream Cost Reconciliation Account, with an equal and offsetting amount to be<br />

credited to the delivery margin the revenue account for a limited period as a unique and unusual transaction<br />

in the circumstances of the SCP and the termination of the BC Hydro TSA. The debiting and the crediting will<br />

commence on either November 1, 2005 or January 1, 2006, as consistent with the amount of the BC<br />

Hydro/Terasen Inc. TSA revenue that Terasen Gas forecast in its Annual Review submission for 2005 and will<br />

end on the earlier of the November 1, <strong>2010</strong> or such other date as the Commission may determine.”<br />

The Settlement Agreement continues to include the annual charge of $3.6 million against the MCRA with an<br />

offsetting credit to the delivery margin. In Commission staff’s view, extending this treatment beyond<br />

November 1, <strong>2010</strong> as contemplated by Order G‐98‐05 requires a determination by the Commission Panel.<br />