3-85 | EPC Template
3.1.2 all design and engineering activities and services necessary to obtain all
required permits for the construction and operation of the Facility;
3.1.3 all construction activities and services necessary to conduct the Work and
complete the Facility in accordance with this Agreement (including Site preparation,
excavation and grading and proper disposal of all excavated materials if and as required
in connection with performance of the Work);
3.1.4 all materials necessary to conduct the Work and complete the Facility in
accordance with this Agreement (including all necessary transport thereof);
3.1.5 all work forces necessary to conduct the Work and complete the Facility in
accordance with this Agreement (including all skilled and unskilled labor, supervisory,
quality assurance and support service personnel);
3.1.6 all documents required to direct Owner’ personnel in the proper start-up,
operation and maintenance of the Facility, including, without limitation, the Equipment
Instruction Manual and all as-built drawings and as-built wiring diagrams (in CD-ROM
format capable of generating reproducible hard copies, stamped by an Architect/Engineer
registered in [Jurisdiction of Facility and/or other]
3.1.7 all training of Operator adequate to allow Operator to assume responsibility
for dispatch and control of the Facility;
3.1.8 all other activities, services and items, whether or not specifically described
above, in Schedule VII or elsewhere in this Agreement, if such performance, provision or
procurement is necessary for a complete and operable Facility; provided, that Contractor
shall not be responsible for performing, providing or procuring those activities, services
and items for which Owner bear express responsibility pursuant to Article 5;
3.1.9 all design, engineering, materials, work forces needed to perform the
Acceptance Tests; and
3.1.10 all activity necessary to enable Contractor to achieve the agreed
Commercial Operation Date of [Deadline for commercial operation] .
ARTICLE 4 - CONTRACTOR’S RIGHTS AND RESPONSIBILITIES
4.1 - Engineering, Procurement and Construction of the Facility; Performance of the
Work. Contractor, on behalf of the Owner, shall act as the general contractor for the
Project and shall be solely responsible for the engineering, procurement and construction
of the Work, including, without limitation, the overall oversight and coordination of
construction of the Facility in accordance with: (a) the Specifications; (b) the
Authorizations for the Facility; (c) the terms of this Agreement; (d) the Traffic Control
Plan, the Safety Plan and the Security Plan; and (e) all applicable Laws. Contractor shall
coordinate the activities of Engineer, PM/CM, the Prime Subcontractors, the Safety
Director, the QA/QC Director and other persons providing labor and materials to the
Project to design, engineer and procure the equipment and materials for and complete the
construction of the Facility and act as the interface between the Owner and such persons
all in accordance with applicable Law and Good Utility Practice.
4.2 - Retention of Qualified Subcontractors and Suppliers Contractor may subcontract
any portion of the Work to one or more Subcontractors and Suppliers. Approved
Subcontractors and Suppliers as of the date hereof are set forth in Schedule VIII.