ENGINEERING, PROCUREMENT &

CONSTRUCTION (EPC)

EPC CONSTRUCTION

MANAGEMENT

Manual

Document

Page

Issue Date

3-252

EPC

TFC-EPC-CM-C-13, REV A

20 of 25

DRAFT 6/09/2015

PS will receive proposal(s) and distribute.

PS will review and approve the subcontractor technical proposal in accordance

with TFC-BSM-CP_CPR-C-05.

Ensure appropriate team members review the subcontractor

proposal(s).

PM will fill out and submit the applicable Technical

Evaluation form to the PS.

PS will process the subcontract release and notify the

subcontractor.

Perform distribution of the notice of award.

E. Pre-Construction/Mobilization

PM will inform the PS of readiness to proceed.

PS will prepare, issue, and distribute Notice to Proceed.

TCM will prepare a letter to the subcontractor for Pre-Construction (Kick-Off)

Meeting with agenda found in TFC-PRJ-CM-C-05.

Submit the Pre-Construction (Kick-Off) Meeting letter to C&C

Document Control.

C&C Document Control distributes Pre-Construction

(Kick-Off) Meeting letter.