17.09.2020 Views

Total-EPC-Book=180920

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

3-99 | EPC Template

10.3 Commercial Operation. “Commercial Operation” shall be deemed to have occurred

as of the first point in time after (i) Mechanical Completion of the Facility has occurred,

as determined by the Independent Engineer; (ii) completion of Acceptance Testing

pursuant to Section 11.2, or alternatively satisfaction of Contractor’s Acceptance Test

related obligations in Section 11.3 (including, if applicable, payment of liquidated

damages pursuant to Section 11.3); and (iii) when the Facility is used and useful for the

purpose of delivering electric energy to Owner (other than electric energy delivered

during Facility Start Up and Acceptance Testing). If the Owner disputes that

Commercial Operation has occurred, it shall provide written notice to that effect to

Contractor, specifying the basis for disputing Commercial Operation and the Parties in

dispute shall thereafter utilize the dispute resolution procedures in Article 12 to resolve

the dispute. Failure of the Owner to provide such written notice within ten (10) Business

Days after receipt of notice of Commercial Operation shall constitute waiver of the

Owner’s right to dispute that Commercial Operation has occurred.

10.4 Punch List. A list of the uncompleted items for the Project shall be established by

Contractor prior to Mechanical Completion (the “Punch List”). The Punch List may be

amended from time to time, upon written Agreement of the Parties, prior to Final

Completion. The Punch List shall include all deliverables through Final Completion.

The “Punch List Holdback Amount” shall be two times the aggregate of the value of the

Punch List items agreed to by the Parties, or determined by the Independent Engineer, if

the Parties cannot agree. The Punch List Holdback Amount shall be withheld from

payments due upon Mechanical Completion, and the agreed value of each Punch List

item shall be paid to Contractor upon completion of the Punch List item and any

remaining Punch List Holdback Amount shall be paid to Contractor upon completion of

all Punch List items.

10.5 Final Completion. “Final Completion” occurs after Commercial Operation has

occurred and any remaining Punch List items have been finished. Contractor will notify

Owner when it considers that Final Completion has occurred. If the Owner disputes that

Final Completion has occurred, it shall provide written notice to that effect to Contractor

specifying the basis for disputing Final Completion and the Parties in dispute shall

thereafter use the dispute resolution procedures in Article 12 to resolve the dispute.

Failure of the Owner to provide such written notice within 10 Business Days after the

initial notice from Contractor shall constitute waiver of the Owner’s rights to dispute that

Final Completion has occurred.

ARTICLE 11 - ACCEPTANCE TESTING; CAPACITY GUARANTEE;

COMPLETION GUARANTEE; WARRANTIES; LIMITATION OF LIABILITY

11.1 Acceptance Tests. Contractor will be responsible for coordinating the Acceptance

Tests of the Facility as more particularly set forth in Section 11.2 and Schedule III of this

Agreement (the “Acceptance Tests”). Such Acceptance Tests shall be conducted by one

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!