3-95 | EPC Template

Work by the Utility Regulator, which shall be handled in accordance with Section 14.l;

(c) any increase or decrease in the Cost of the Work resulting from any Change Order

made pursuant to Section 8.4, 8.5, or 8.8, which shall be allocated as set forth in such

Sections; and (d) any increase in the Cost of the Work resulting from the Owner’s failure

to cooperate reasonably with Contractor the other Parties to this Agreement, including

without limitation owner’s failure to carry out its duties under Sections 5.2 or 5.4.

ARTICLE 8 - ADDENDA AND CHANGE ORDERS

8.1 General. “Addenda” are changes to the Work before construction begins. “Change

Orders” are changes to the Work after construction begins. Addenda and Change Orders

shall be handled as follows:

8.1.1 Any Party may request an Addendum or Change Order in writing.

8.1.2 Approval or rejection of Addenda and Change Orders that increase or

decrease the Cost of the Work or change in schedule that could have the effect of

delaying Mechanical Completion must be approved by Owner and Contractor prior to

execution of such Addenda or Change Order.

8.1.3 Addenda and Change Orders that increase or decrease the Cost of the Work

shall be approved or rejected in accordance with the procedures set forth in Sections 8.2

and 8.3 and in accordance with the time periods provided for the State in Section 16.20.

8.2 Process. Any of the Parties may request in writing an Addendum or a Change Order

consisting of additions to, deletions from, or other revisions to the Work, provided that

such changes are within the general scope of the Work. All requests for Addenda or

Change Orders by an Owner shall be submitted to Contractor, with copies to PM/CM and

Engineer (as appropriate). All requests for Addenda or Change Orders by Contractor

shall be submitted to Owner, with copies to PM/CM and Engineer.

8.3 Initial Evaluation of Addendum and Change Order Requests; Applicable Standards.

Any Addendum or Change Order request from an Owner shall be evaluated by

Contractor, with the input and assistance of PM/CM and Engineer. Each Addendum or

Change Order request shall initially be evaluated to determine whether it: (a) adds value

to the Facility without increasing the Cost of the Work or delaying Mechanical

Completion of the Facility; (b) adds value to the Facility without delaying Mechanical

Completion of the Facility, but increases the Cost of the Work; or (c) does not add value

to the Facility or adds value to the Facility, but will delay Mechanical Completion of the

Facility or compromise performance of the Facility; or (d) (in the case of an Addendum

only) decreases Cost of Work without delaying Mechanical Completion. All Addenda

and Change Orders in category (a) or Addenda in category (d) shall be approved; all

Addenda and Change Orders in category (c) shall be rejected (unless mutually agreed

otherwise, including the allocation of the cost, by all Parties); and all Addenda and

Change Orders in category (b) shall be approved, if and only if the increased Cost of the

Work is allocated as set forth below in this Article 8.

8.4 Addenda or Change Orders Requested by Owner. If Owner requests an Addendum

or a Change Order to address solely Owner’s needs, including without limitation changes