ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
3-233
EPC
TFC-EPC-CM-D-13, REV A
1 of 25
DRAFT January 31, 2017
This guide describes suggested non-mandatory approaches for meeting requirements. Guides are
not requirements documents and are not construed as requirements in any audit or appraisal for
compliance with the parent policy.
TABLE OF CONTENTS
1.0 PURPOSE AND SCOPE ................................................................................................................ 2
2.0 IMPLEMENTATION ..................................................................................................................... 2
3.0 RESPONSIBILITIES ...................................................................................................................... 2
4.0 PROCEDURE ................................................................................................................................. 2
4.1 Process Work Flow Chart ................................................................................................... 2
4.2 Process Work Flow – WRPS acting as PM/Constructor .................................................... 2
4.3 Process Work Flow – WRPS as PM/CMT ......................................................................... 9
5.0 DEFINITIONS .............................................................................................................................. 15
5.1 Administrative change ...................................................................................................... 15
5.2 Construction Representative ............................................................................................. 15
5.3 Non-administrative change. .............................................................................................. 15
5.4 Issue Authorization and Maintenance for Use .................................................................. 16
5.5 Project Management/Constructor Team (PM/Constructor).............................................. 16
5.6 Project Management & Construction Management Team (PM/CMT)............................. 16
6.0 RECORDS .................................................................................................................................... 16
7.0 SOURCES ..................................................................................................................................... 17
7.1 Requirements .................................................................................................................... 17
7.2 References ......................................................................................................................... 17
TABLE OF FIGURES
Figure 1. Process Work Flow Chart. ......................................................................................................... 19
Figure 2. Construction Execution Process Work Flow Chart. ................................................................... 24
Figure 3. Construction Action Log Process Work Flow Chart. ................................................................. 25