4.5.2 Contractor shall be responsible for assuring that all waste generated in the
performance of its obligations under this Agreement and all waste transported to or from,
moved or used or stored upon the Site by Contractor or any other person for whom
Contractor is responsible, within the scope of Contractor’s performance of this
Agreement, is handled in accordance with applicable Law. Contractor shall cause the
affected Subcontractors to manage and dispose of the waste in compliance with
applicable Law and Good Utility Practice.
4.5.3 Contractor shall be responsible to see that all sedimentation, erosion
control, and siltation within or adjacent to the Site caused by Subcontractors is conducted
in accordance with applicable Law. In the event Contractor fails to prevent such
sedimentation, erosion or siltation from occurring in violation of applicable Law, Owner
shall have the right, after notifying Contractor and providing it an opportunity to cure of
not less than three (3) Business Days, to correct such pollution or siltation. All expenses
incurred by the Owner in the course of such correction shall be credited against payments
owed to Contractor.
4.6 Compliance with Laws In carrying out its duties hereunder, Contractor shall comply
with all applicable Laws, including without limitation, all Laws relating to health, safety
or the protection of the environment. Owner shall have no responsibility for any costs of
environmental compliance or remediation to the extent caused by the negligent acts and
omissions or intentional or willful misconduct of Contractor or any of Contractor’s
employees or agents, including, without limitation, all Subcontractors and Suppliers.
4.7 Traffic Control Plan. Contractor shall work together with Owner to develop a
comprehensive traffic control plan for the Project (“Traffic Control Plan”), to assure all
persons supplying the Work prompt and safe access for deliveries to the Site, while
minimizing disruption to the surrounding area its regular activities or scheduled events.
Without limitation, the Traffic Control Plan shall provide, as required by the surrounding
areas and its activities: (a) for off-site parking for construction personnel and transport of
such personnel to the Site; (b) a general prohibition on deliveries of Major Equipment to
the Site during the hours of [Hours,] ; (c) that Contractor shall use its reasonable efforts
to arrange for deliveries of Major Equipment [Days and hours] ; and (d) that it shall be
consistent with any traffic control requirements set forth in any Governmental
Authorization. Owner shall use good faith efforts to assist Contractor in the development
of this plan and to assist in gaining for Contractor access to roads and other transportation
facilities necessary for timely and cost-effective completion of the Project. When
available, the draft traffic control plan shall be presented to Owner for review and
approval. Contractor acknowledges that it has studied the Site, railroads, surrounding
streets and highways and Contractor can transport all equipment to the Site and all costs
associated with the transportation and unloading of the equipment are included in the
Guaranteed Maximum Price, provided that access to the Site is available to Contractor
and the Subcontractors at all reasonable times and in accordance with the Traffic Control
Plan. Contractor shall provide to Owner its proposed Traffic Control Plan no later than
30 days following the date of this Agreement. The Parties shall use their good faith
efforts to finalize the Traffic Control Plan no later than 60 days following the date of this
Agreement.