ENGINEERING, PROCUREMENT &

CONSTRUCTION (EPC)

EPC CONSTRUCTION

MANAGEMENT GUIDE

Manual

Document

Page

Issue Date

3-235

EPC

TFC-EPC-CM-D-13, REV A

3 of 25

DRAFT January 31, 2017

expectations required of the subcontractor. Acquisition planning requirements and process are

defined in TFC-BSM-CP_CPR-C-05.

Action by

Project Manager

Project Manager/BTR

Construction Manager

Project Manager

Action

1. Involve the CM or designee in the Acquisition Planning Process.

2. Authorize pre-construction and subcontract execution activities.

3. Initiate pre-construction activities.

4. Conduct a meeting with appropriate Team members and

Procurement personnel to identify how the work will be

subcontracted.

B. Constructability

Constructability reviews should be performed for all projects. The goal of the constructability

reviews is to optimize benefits to the entire project, not just to a single department or discipline.

Action by

Action

CM 1. Ensure Construction participates and performs constructability

reviews on projects and the design documents per TFC-EPC-

CM-D-01.

C. Construction Statement of Work

The Construction SOW document is a critical procurement document that defines the work scope,

processes and requirements of the subcontractor so completed construction work achieves TOC

expectations.

TFC-PRJ-CM-C-18 defines the process for developing a SOW and the contents necessary for

inclusion in the SOW.

Action by

Action

Project Manager/BTR 1. Provide the definition of the work to be performed by a

subcontractor to the CM.

CM 2. With concurrence of the Project Manager, determine who is

best suited to be assigned the responsibility of the SOW

Coordinator.

SOW Coordinator 3. Develop the SOW and related appendices in accordance with

TFC-PRJ-CM-C-18.

D. Request for Proposal Issuance and Subcontract Award

The process for procurement of a subcontractor, from SOW entry into Asset Suite, approval

process, issuing an RFP, through subcontract award is addressed in TFC-BSM-CP_CPR-C-05.

The Team will assist procurement during this process by reviewing technical requirements and

providing answers to subcontractor questions during the proposal phase. The Team will also