17.09.2020 Views

Total-EPC-Book=180920

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

3-105 | EPC Template

12.2 Continued Performance. During the conduct of dispute resolution procedures

pursuant to this Article 12, (a) the Parties shall continue to perform their respective

obligations under this Agreement, and (b) no Party shall exercise any other remedies

hereunder arising by virtue of the matters in dispute.

ARTICLE 13 - DEFAULTS; REMEDIES; TERM; TERMINATION

13.1 Contractor Default. The occurrence of any of the events set forth below shall

constitute a “Contractor Event of Default” under this Agreement:

13.1.1 Bankruptcy. Contractor becomes insolvent, or become the subject of any

bankruptcy, insolvency or similar proceeding, which, in the case of any such proceeding

that a third party brings against either of them, has not been terminated, stayed, or

dismissed within 60 Business Days after it was commenced, unless the affected Party

provides evidence to Owner of that Party’s ability to perform all of its obligations under

this Agreement; or

13.1.2 Failure to Maintain Insurance. Contractor fails to maintain the insurance

coverages required under Section 4.20 as set forth in Schedule II hereto; or

13.1.3 Failure to Perform. Contractor shall have defaulted in its performance

under any other material provision of this Agreement and shall have failed to cure such

default within 30 days following delivery to Contractor of a Notice from Owner to cure

such default, or if a cure cannot be effected within such 30 day period, such period shall

extend for a reasonable period of time, but not to exceed a total of 60 days, so long as

Contractor is proceeding diligently to cure such default throughout such period; or

13.1.4 Representation False. Any material representation made by Contractor

herein shall have been false or misleading in any material respect when made; or

13.1.5 Failure to Achieve Mechanical Completion. If Mechanical Completion is

not achieved by the Delay Default Date; or

13.1.6 Failure to Obtain Authorization. The Project cannot proceed to completion

as the ultimate result of a refusal of Governmental Authority to approve the Project or

any other Authorization, which refusal is due solely to the negligence or willful

misconduct of Contractor.

13.2 Owner’s Default Remedies Against Contractor. If a Contractor Event of Default

shall have occurred and be continuing, either Owner shall have the right to terminate this

Agreement by notice to Contractor. In the event of such termination:

13.2.1 If requested by an Owner, Contractor shall withdraw from the Site, shall

assign to the Owner (without future recourse to Contractor) such of Contractor’s

subcontracts as Owner may request, and shall remove such materials, equipment, tools

and instruments used and any debris or waste materials generated by Contractor in the

performance of the Work as Owner may direct, and Contractor shall promptly deliver to

Owner all designs, drawings, and other documents related to the Project. In the event of

such termination, Contractor shall deliver to Owner all materials and data for which title

has passed to Owner. To the extent any specific item of the Work is partially complete at

the time of termination, at the option of either Owner, Contractor shall complete such

partially completed Work. In such event, Owner shall pay Contractor the amount that

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!