ENGINEERING, PROCUREMENT &

CONSTRUCTION (EPC)

EPC CONSTRUCTION

MANAGEMENT GUIDE

Manual

Document

Page

Issue Date

3-246

EPC

TFC-EPC-CM-D-13, REV A

14 of 25

DRAFT January 31, 2017

J. Construction Acceptance Testing and Turnover

CMT Action by Action

Approve

Commissioning

Manager

1. Ensure CAT(s) are developed in accordance with

TFC-EPC-CM-C-17.

Oversight CM 2. Ensure CAT(s) are performed in accordance with

TFC-EPC-CM-C-17.

3. After notification from the subcontractor that the

work is substantially complete, notify the

following;

• Task Project Manager

• Manager of Construction

• Commissioning Manager

• Testing Lead

• Work Area Construction Manager

• BTR

• Other entities as deemed appropriate.

K. Construction Completion and Turnover

CMT Action by Action

Oversight/Approve CM 1. Ensure completion and transfer is performed in

accordance with TFC-EPC-CM-D-11, and TFC-

PRJ-CM-C-08.

L. Subcontract Closeout

CMT Action by Action

Approve CM 1. Ensure subcontractor closeout is performed in

accordance with TFC-PRJ-CM-C-15 and ensure

the “Construction Subcontract Closeout

Checklist” (CSCC) Form (A-6003-226) is

complete.