3-96 | EPC Template

to address aesthetic or design requirements, and such Addendum or Change Order is

approvable under Section 8.3 above and approved by Contractor, but increases the Cost

of the Work, then Owner shall bear the entire incremental Cost of the Work (including

costs of delays and rework) resulting from such Addendum or Change Order.

8.5 Addenda and Change Orders Required by Acts of Governmental Authorities. If any

action of any Governmental Authority requires an Addendum or a Change Order that

increases or decreases the Cost of the Work the Owner shall be responsible for any

incremental Cost of the Work.

8.6 Addenda and Change Orders Requested by Contractor. If Contractor requests an

Addendum or a Change Order that is approved by the Owner, then Owner and Contractor

shall share equally any increase or decrease in the Cost of the Work resulting from such

Addendum or Change Order.

8.7 Addenda and Change Orders Resulting from Errors or Omissions of Contractor.

Owner shall not be responsible for any increased Cost of the Work resulting from

Addenda and Change Orders that are necessary because of errors of Contractor and/or its

Subcontractors in coordinating the design, scheduling or construction of the Facility.

8.8 Markup on Addenda and Change Orders. On any Addenda and Change Orders under

Sections 8.4, and 8.5, Contractor and its Subcontractors shall be entitled to a markup not

to exceed ten percent (10%) in the aggregate of the Cost of the Work covered by the

Addendum or Change Order.

8.9 Tracking of Cost Impact of Addenda and Change Orders. Contractor shall institute

and maintain a ledger type system to track the impact of all increases and decreases to the

Owner’ Allocated Shares of the Cost of the Work resulting from any Addenda or Change

Orders approved by Contractor and Owner. Contractor shall monthly, and more

frequently upon request, report to the Owner the cumulative impact of such Addenda and

Change Orders upon their respective Allocated Shares of the Cost of the Work. If

applicable, the Parties shall modify the Project Schedule and Payment Milestones to

reflect the impact of Addenda and Change Orders.

ARTICLE 9 - PAYMENT FOR WORK

9.1 Payment Milestones; Payment Schedule.

9.1.1 Progress Report and Invoice.

9.1.1.1 On or about the fifth Business Day of each calendar month, Contractor

shall submit to Owner (i) its invoice, and (ii) a progress report covering the previous

calendar month (the “Payment Period”) containing at a minimum the following

information (“Progress Report”): (1) A description of the Work performed during the

Payment Period and all Payment Milestones achieved; (2) A description of the Work not

yet performed, if any, necessary to meet the Project Schedule for such Payment Period;

(3) A description of the Work and the related Payment Milestones anticipated to be