ENGINEERING, PROCUREMENT &
CONSTRUCTION (EPC)
EPC CONSTRUCTION
MANAGEMENT GUIDE
Manual
Document
Page
Issue Date
3-237
EPC
TFC-EPC-CM-D-13, REV A
5 of 25
DRAFT January 31, 2017
Action by
Action
Procurement Specialist/BTR 7. Obtain necessary clearances and keys for the subcontractor so
mobilization can proceed (the subcontractor obtains any
badges, clearances, dosimeters, etc.).
F. Contract Execution
Figure 2 illustrates the process flow related to construction execution.
G. Construction Execution
Documentation for various construction documents shall be in accordance with TFC-BSM-
IRM_DC-C-07. All construction communication documents will be submitted to ^LAWPS
VENDOR at LAWPSVENDOR@rl.gov.
H. Execution of the SOW
Action by
Project Manager
CM and BTR
Action
1. Review subcontractor planned work and ensure necessary field
support through the CM.
2. Ensure that all subcontract submittals required prior to start of
construction work and baseline construction schedule have been
received.
3. Ensure that the Design Document List (DDL) is complete and
the Work Breakdown Structure (WBS) authorizations and
assignments have been made.
4. The team will have oversight and monitoring responsibility for
safety, quality, progress, cost, change control, and compliance
with EPC guides.
CM or Designee
5. Assist the subcontractor performing the work in all matters
pertaining to the work and ensure the work performed follows
the SOW while being in compliance with applicable TOC and
EPC procedures.
6. Ensure subcontractor understands what work, if any, will be
performed under the work package planning guide TFC-EPC-
CM-C-03.
7. Assist the Procurement Specialist, BTR and/or Project Engineer
in performance of the following:
• Track submittals.
• Initiate, track, and status subcontractor back-charges per
TFC-PRJ-CM-C-12.