7. การตรวจเยี่ยมสถานที่ก่อสร้าง

DRB Visit No. __; Agenda

1. Scope of maintenance activities required under Clause 3. 1 of

Technical Specification No. 1 (Volume 2.1).

2. Interpretation of the Method of Calculation for IPC 43.

3. Interpretation of Method of payment for IPC 43.

4. Employer to advise DRB regarding the status of ongoing discussions

with the Contractor pursuant to the Employer’s Notice of Dispute

issued on [DATE].

On being advised that senior members of the Employer’s and the

Contractor’s staffs planned to attend the following day especially to

discuss Agenda Items 2, 3 and 4 concerning the method of

calculation of IPC 43 for interpretation of Addendum No. 2 to the

Contract, the DRB took up the Agenda Item No. 1.

As a general matter, the DRB was advised that good progress was

being made on the Works at the Underpass and that the Contractor

expects to meet the date for its substantial completion.

Agenda Item 1. Scope of maintenance activities required under

Clause 3.1 of Technical Specification No. 1 (Volume 2.1).

The matter of the Contractor’ s Maintenance Obligations required

under Clause 3. 1 of the Technical Specification was discussed at

length during the most recent Site Visit. The DRB had recommended