08.01.2013 Views

Steel Designers Manual - TheBestFriend.org

Steel Designers Manual - TheBestFriend.org

Steel Designers Manual - TheBestFriend.org

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

This material is copyright - all rights reserved. Reproduced under licence from The <strong>Steel</strong> Construction Institute on 12/2/2007<br />

To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.<strong>org</strong>/<br />

<strong>Steel</strong> <strong>Designers</strong>' <strong>Manual</strong> - 6th Edition (2003)<br />

974 Erection<br />

it offers provides a unique vehicle for the incorporation of a wide range of construction<br />

expertise into the design process, with the ultimate objective of achieving<br />

building designs and construction which offer clients better value for money.<br />

33.3.2 Programming<br />

Resources can be best utilized when the delivery and erection operations are well<br />

planned to follow a logical sequence. Typically, civil and other trades need to be sufficiently<br />

ahead of the steel erection (i.e. one week minimum) to allow for a reasonable<br />

flow of uninterrupted work. This will allow the steelwork contractor time to<br />

survey the foundation bolts prior to accepting them. It is not unusual for the civil<br />

contractor to have to carry out minor remedial work due to poor alignment of the<br />

holding-down bolts, and to this end it is advisable to allow the maximum time<br />

possible for handovers. Accurate positioning of foundations is essential, and<br />

tolerances defined in the specification and the National Structural <strong>Steel</strong>work<br />

Specification (NSSS) 3 should be strictly adhered to.<br />

Access restrictions or phasing of the works often govern the sequence of<br />

erection, which normally follows a grid pattern, split into zones. The siting of the<br />

erection crane will also dictate the construction pattern. Once the sequence and<br />

phasing have been agreed, the steelwork contractor can determine the resources<br />

required to meet the programme.<br />

33.3.3 Delivery and off-loading of steelwork<br />

A construction sequence programme is agreed prior to delivery of any materials to<br />

site, from which a delivery schedule may be produced. A more detailed piece-bypiece<br />

schedule for the steel erection method will need to be carried out to ensure<br />

smooth working on site. Particular attention should be paid to the logistics of this<br />

exercise to prevent members being missed out, double handling of materials on site,<br />

lorries being under-utilized, and the positioning of steel in the wrong location.<br />

Delivery of the steelwork is normally in 20-tonne lorry loads, often sub-divided<br />

into four bundles of 5 tonnes each to suit tower crane capacity, on a ‘just in time’<br />

delivery sequence in order to alleviate site congestion, and minimize double handling<br />

and on-site damage. Material needs to be stacked in the lorry for easy offloading,<br />

with items that are needed first, readily available. Often the loading of the<br />

lorry can be dictated by crane off-loading capacity or stability of the load as columns<br />

are usually required first, yet they need to be at the bottom of the load because of<br />

their weight.<br />

Shakedown areas (areas for separating and selecting steel bundles) are required<br />

on site to allow the sorting of the steelwork. The area should be firm and level with<br />

a plentiful supply of wooden sleepers or other suitable material. The steel members

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!