08.01.2013 Views

Steel Designers Manual - TheBestFriend.org

Steel Designers Manual - TheBestFriend.org

Steel Designers Manual - TheBestFriend.org

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

This material is copyright - all rights reserved. Reproduced under licence from The <strong>Steel</strong> Construction Institute on 12/2/2007<br />

To buy a hardcopy version of this document call 01344 872775 or go to http://shop.steelbiz.<strong>org</strong>/<br />

<strong>Steel</strong> <strong>Designers</strong>' <strong>Manual</strong> - 6th Edition (2003)<br />

Economy is generally linked to the use of standard rolled sections but, with the<br />

advent of automated cutting and welding equipment, special fabricated sections are<br />

becoming economic if there is sufficient repetition.<br />

The development of efficient, automated, cold-sawing techniques and punching<br />

and drilling machines has led to the fabrication of building frameworks with bolted<br />

assemblies. Welded connections involve a greater amount of handling in the fabrication<br />

shop, with consequent increases in labour and cost.<br />

Site-welded connections require special access, weather protection, inspection<br />

and temporary erection supports. By comparison, on-site bolted connections enable<br />

the components to be erected rapidly and simply into the frame and require no<br />

further handling.<br />

The total weight of steel used in continuous frames is less than in semicontinuous<br />

or simple frames, but the connections for continuous frames are more<br />

complex and costly to fabricate and erect. On balance, the cost of a continuous frame<br />

structure is greater, but there may be other considerations which offset this cost<br />

differential. For example, in general the overall structural depth of continuous<br />

frames is less.This may reduce the height of the building or improve the distribution<br />

of building services, both of which could reduce the overall cost of the building.<br />

Corrosion protection to internal building elements is an expensive and timeconsuming<br />

activity. Experience has shown that it is unnecessary for most internal<br />

locations and consequently only steelwork in risk areas should require any protection.<br />

Factory-applied coatings of intumescent fire protection can be cost-effective<br />

and time-saving by removing the operation from the critical path.<br />

Construction<br />

Factors influencing choice of form 55<br />

Fig. 2.10 Structural costs: (a) economic and (b) uneconomic layouts<br />

A period of around 8–12 weeks is usual between placing a steel order and the arrival<br />

of the first steel components on site. Site preparation and foundation construction<br />

generally take a similar or longer period (see Fig. 2.11). Hence, by progressing fabrication<br />

in parallel with site preparation, significant on-site construction time may<br />

be saved, as commencement of shop fabrication is equivalent to start-on-site for an<br />

in situ concrete-framed building. By manufacturing the frame in a factory, the risks

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!